Upcoming
November 2024
Complete construction (anticipated)
September 28 - October 20 2024
Temporary traffic detours of Route 28 (Sully Road) / McLearen Road on and off ramps (Saturday and Sunday mornings from sunrise to 9:00 a.m.)
August 24 - September 22 2024
Temporary traffic detours of Route 28 (Sully Road) / Air and Space Museum Parkway on and off ramps (Saturday and Sunday mornings from sunrise to 9:00 a.m.)
2024
August 3 - August 18
Temporary traffic disruptions on Route 28 (Sully Road) on Saturday and Sunday mornings from sunrise to 9:00 a.m.
March 2024
Begin energized reconductor work
2023
November - December 2023
Reconductor short segments of the line near Walney Substation and Sully Historic Site
Late 2023
Replace two structures near Cub Run Substation