Powerlines

Edsall

Substation and Transmission Line Project
Dominon Energy is working with the community to plan a new substation and transmission line project in Fairfax County.  Explore the project, views maps and updates, and share your feedback as planning moves forward.

Project Details

Dominion Energy is proposing a new substation and transmission line project in Fairfax County to help meet growing energy needs.  Explore maps, visual simulations, project updates, timelines, and opportunities to provide feedback. 

Benefits

  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Minimizes impact to the community and environment
  • Strengthens area reliability

Documents

Substation Noise Tool App

Community Involvement

Public Engagement Process

Dominion Energy is proposing a new substation and transmission line project in Fairfax County to help meet growing energy needs.  Explore maps, visual simulations, project updates, timelines,Dominion Energy is proposing a new substation and transmission line project in Fairfax County to help meet growing energy needs.  Explore maps, visual simulations, project updates, timelines, and opportunities to provide feedback.  and opportunities to provide feedback. 

NOVA Virtual Open House

See all the latest information on Dominion Energy's project in Northern Virginia, including the Edsall Substation.
Go to the virtual open house cta btn

What Matters To You?

Explore GeoVoice, an interactive mapping tool. You can:

  • Search for your address
  • Explore proposed project routes
  • Send comments to the project team
We want to hear from you. Sign-up today. Access GeoVoice here. cta btn

Legal

SCC Application

The Virginia State Corporation Commission (SCC) has regulatory authority over all energy providers in Virginia. Among other responsibilities, the SCC validates the need for a proposed line and approves the route and structures. In reviewing a proposed project, the SCC must consider whether potential impacts on scenic assets, historic districts and the environment have been reasonably minimized. On July 26, 2024, Dominion Energy filed its application with the SCC. The SCC issued its Final Order approving the project on August 8, 2025.

Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2024-00135 in the "Search Cases" section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments.

Timeline

(anticipated - subject to change)

2028

Q3 2028
Restoration begins
Q2 2028
Edsall Project energization

2027

Q3 2027 - Q1 2028
Transmission line construction
Q2 2027 - Q2 2028
Substation construction

2025

August
 Received SCC Final Order

2024

May
Submitted application to the Virginia State Corporation Commission (SCC)

Construction-Related Impact

Low impact symbol

Service Interruption

Your electric service is not expected to be impacted by this project.
Low impact symbol

Traffic

This project is not expected to impact traffic.
Low impact symbol

Noise

Noise levels will be minimal; permits are in place.
Medium impact symbol

Environment

This project may have limited environmental impacts.
Medium impact symbol

Neighborhood

Access to surrounding neighborhoods may be impacted.