success-icon
The redesigned DominionEnergy.com is here!: A fresh look, easier navigation, and enhanced search features make it easier than ever to find the information you need.

Lineworker in front of Dominion Energy truck

Nimbus 230 kV Delivery

This substation, along with new transmission infrastructure is needed to accommodate load growth and to maintain reliable electric service in the area.

Rapid growth in electrical demand, particularly in the commercial/high-tech sector in eastern Loudoun County has resulted in the need to build a new transmission line and sub station. This project will improve electric reliability for all customers in the region.

At Dominion Energy, we are committed to reviewing and analyzing our energy infrastructure and doing this work safely to provide reliable electric service. Three primary forces drive the need for new electric transmission infrastructure:

  • Economic development, such as population growth or business expansion
  • Aging assets, such as decades old structures that need to be replaced
  • Complying with mandatory standards to ensure safety and reliability

These drivers often overlap, and at Dominion Energy, we believe solutions should always account for future energy needs while continuing to balance cost and impacts.

Benefits

  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Minimizes impact to the community and environment

Documents

Simulations

Service Interruption

Your electric service is not expected to be impacted by this project.

Neighborhood

Access to surrounding neighborhoods will not be impacted.

Traffic

This project is not expected to impact traffic.

Noise

Noise levels will be minimal; permits are in place.

Environment

This project will not have environmental impacts.

SCC

The Virginia State Corporation Commission (SCC) has regulatory authority over all energy providers in Virginia. Among other responsibilities, the SCC validates the need for a proposed line and approves the route and structures. In reviewing a proposed project, the SCC must consider whether potential impacts on scenic assets, historic districts and the environment have been reasonably minimized.

On 2/23/22, Dominion Energy filed its application with the SCC. The SCC issued its Final Order approving the project on 10/14/22. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2022-00027 in the " Search Cases " section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments.

SCC Application

Virtual Community Meeting live via Webex Events

2025

PHASE 2: 2025
Build new single circuit 230 kV electric transmission line to connect existing Farmwell Substation to new Nimbus Substation

2023

PHASE 1: SUMMER 2023 – DECEMBER 2024
July 2023 - Nimbus Substation site preparation, including building a retaining wall for soil stability; 2024 - Build new double circuit 230 kilovolt (kV) electric transmission line to connect an existing transmission line to Nimbus Substation along the south side of Waxpool Road

2022

February 3, 2022
Virtual Community Meeting
February 2022
Project filed with the SCC

2021

November 2021–February 2022
Outreach to the community

Powerlines 101 - Learning Zone

Learn how the energy grid works; along with our processes to build and maintain electric transmission lines.
Discover about your lines cta btn