After nearly 100 years of reliable service, an 11-mile section of electric transmission line built on galvanized steel lattice structures between Craigsville and Goshen substations needs to be replaced to maintain safety and electric reliability for our customers.

Project Overview Map

Benefits & Timeline

Benefits

  • Maintains current right of way
  • New structures located in the same general location as existing structures
  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Minimizes impact to the community and environment
  • Replaces aging infrastructure

Timeline

  • November 2021 – Announce project to community
  • Q4 2021 – Q1 2022 – Develop project plans and coordinate with localities and stakeholders
  • May 2023 – Hold construction informational meeting with community
  • Summer 2023 – Begin construction
  • End of 2024 – Complete construction
  • Spring 2025 – Complete restoration