Important Update - September 2023

There will be increased construction activity along Vesper Trail this fall. From mid-September 2023 through the end of October 2023, crews will be crossing the trail throughout the day, and the trail will remain open. From November 1, 2023, through mid-February 2024, the trail will be closed.

Click here to see the most recent update postcard sent to the community.

Keep Up With Construction Progress With Our Interactive Portal

Benefits

  • Complies with mandatory standards to ensure safety, reliability and to meet future needs

Timeline (View Full Timeline)

  • September 29, 2020
    Filed application with SCC
  • March 2, 2021
    Dominion Energy Virginia Rebuttal due
  • March 26, 2021
    Public Comments deadline
  • March 31, 2021
    A local public hearing will convene by telephone at 10 a.m., with no witness present in the Commission courtroom.
    The Commission will telephone each witness sequentially who has signed up to provide comment
  • June 24, 2021
    SCC issued final order, approving the project
  • 2021 – Early 2023
    Permitting and finalize engineering
  • April 2023
    Construction activities begin, interactive portal live

Contact Us

Call us M - F, 8am - 5pm

(888) 291-0190

Construction-Related Impacts

Service Interruption

There are no planned service interruptions for this project