Parallel Generation & Interconnection
How to apply for parallel generation and interconnection to the distribution system
What is Parallel Generation?
"Parallel generation" refers to a generator that produces electricity while it is connected to the electric grid. Your electrician or consultant can tell you whether your generator will operate in parallel.
Generator Interconnection
You'll need permission to interconnect your parallel generator to Dominion Energy’s electric grid. Interconnections must be individually accepted and inspected prior to beginning parallel operation. There are several options available for interconnecting your parallel generator, including net metering or selling the generator output. Specific requirements will vary depending on the state in which your project is located and whether it is a distribution or transmission interconnection.
Ways to Apply for Interconnection
Other Resources
Overview—Interconnection Steps provides a helpful listing of the basic steps for interconnecting your generator.
Virginia Queue Status
The Virginia Queue Status Report will be updated on a quarterly basis. Refer to DISCLAIMER.
Virginia Queue Performance
The Virginia Queue Performance Report will be updated on a semi-annual basis. Refer to DISCLAIMER.
Targeted Cluster Studies
The State Corporation Commission of Virginia issued an Order directing the Company to conduct a pilot examining the use of targeted cluster studies as a possible alternative to, or addition to, the current interconnection study process. Access the pilot notification form.
Interconnection Parameters
The Interconnection Parameters for Distributed Energy Resources (DER) guide includes details of Dominion Energy's DER general study process and parameters, and DER general interconnection parameters.
Customer Generation Requirements
For electric service, consult Dominion Energy’s Blue Book - Information and Requirements. Section 190 of the Blue Book has information regarding customer generation.