Summer 2025
Remington – Rollins Ford Phase 3 and 4 reconductor expected completion
Spring 2025
Remington – Rollins Ford Phase 3 and 4 reconductor begins
Fall 2024
Remington - Rollins Ford Phase 3 and 4 structure lifts begin
Spring 2024
Remington - Rollins Ford Phase II reconductor completed
Early 2024
Remington - Rollins Ford Phase II structure lifts began
Early 2024
Remington - Rollins Ford Phase II reconductor access and construction began
Late 2023
Remington - Rollins Ford Phase I reconductor completed
Fall 2023
Reconductor began at Remington Substation
Summer 2023
Remington - Rollins Ford Phase I access installation began