230 kV Electric Transmission Upgrade and Rebuild Project

Lineworker in front of Dominion Energy truck

Upcoming Survey Activity

To comply with the Endangered Species Act and the United States Fish and Wildlife Service guidelines, we will conduct wildlife surveys along the right of way corridor. Our crews will also survey for encroachments. This activity will begin in the next few weeks and may continue through the fall. During this survey activity, you may see Dominion Energy and/or contractors and equipment near your property and in the transmission right of way. If our crews need to utilize your property to access the right of way, they will come to your door and attempt to speak with you first.

Maps

Use our interactive map tool and enter your address to see where you live in relation to this transmission line rebuild project. This tool will show you existing structure type, proposed structure type, and associated differences. You can also view photo simulations along the line and other important features too.

Benefits

  • New structures located in the same general location as existing structures
  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Minimizes impact to the community and environment
  • Replaces aging infrastructure

Timeline (View Full Timeline)

  • February 2023 – Original project announcement
  • 2nd – 4th Quarters 2023 – Project engineering re-evaluation
  • January 2024 – Phase 1 (Fredericksburg-Aquia Harbour) Announcement
  • February 8, 2024 – Phase 1 (Fredericksburg-Aquia Harbour) Community Meeting
  • March 14, 2024 – Phase 1 application filed with State Corporation Commission (View Legal Page)
  • June 2024 – Phase 2 (Aquia Harbour-Possum Point) Announcement
  • June 18 and 20, 2024 – Phase 2 (Aquia Harbour-Possum Point) Community Meetings Held
  • August 14, 2024 – Phase 2 application filed with State Corporation Commission (View Legal Page)
  • Summer 2025 – Anticipated Phase 1 construction start in City of Fredericksburg and Stafford County

Contact Us

Call us M - F, 8 a.m. - 5 p.m.

888-291-0190

Construction-Related Impacts

Service Interruption

Your electric service is not expected to be impacted by this project.

Aging Infrastructure

70 Years

The equipment has been in service for 70 years and needs to be replaced.  