Summer 2027
Construction complete, restoration of work areas begins
Early 2026
Construction to begin
February 2025
SCC final order approving the project
2025
Permitting, finalize engineering, pre-construction outreach
Early Summer 2024
File application with the Virginia State Corporation Commission (SCC)
March 2024
Community meetings
Early 2024
Project announcement