How can I verify the pressure and/or availability of natural gas for a project?
Contact the person responsible for the area where the project is being constructed. Commercial/Industrial customers will need to provide the BTUs and pressure required for their project. A letter of availability can be provided.
When does Dominion Energy need to be notified to supply gas service to a new project?
The sooner Dominion Energy knows of new projects the process can begin. Early notification will allow Dominion Energy to contract with the customer, receive payment, and coordinate to install gas service in a timely manner. A gas service line can be installed as soon as the building has been backfilled. Average time is 6 to 8 weeks.
What information is required for gas service?
Initially, Dominion Energy requires the following from the person contracting for service:
Are there any special requirements for meters?
The meter set is placed outdoors and the fuel line is run above ground into the building. The meter set shall be accessible to Dominion Energy service personnel and protected from accidental contact. A mounting pad may also be required. The size of this pad is based on the size and type of gas meter installed. Meter protection may be required.
Who is responsible for the installation of the service lines?
Dominion Energy personnel or contracted contractor shall obtain the necessary permits for the service installation and perform the actual installation.
Who is responsible for the installation of the gas service and meter?
Dominion Energy is responsible for the installation and maintenance of the gas service and gas meter.
What is the customer's responsibility?
Dominion Energy is responsible for gas service to, and including, the meter. The customer is responsible for gas lines from the meter to the building, including the inside of the building.
What are the requirements before a meter can be set?
The customer must call Dominion Energy business office (toll-free 800-323-5517) to set up a gas account for gas service. City clearance must be received giving permission for the meter to be set. The cities shall send this clearance to Dominion Energy when they complete their 4-way inspection.
How much will it cost to run gas service to my home/business?
The cost for a new service line will depend on:
Your service representative will be able to answer your questions.
What is meter protection? How do I know if I need meter protection?
If your meter is located where there is a possibility of damage to the meter, meter protection is required. Also, if you have a lot of snow fall in your area, it is important to keep snow from accumulating on the meter and surrounding area. Your service representative will be able to tell you if you need meter protection. Dominion Energy can provide the meter protection. If a customer prefers to provide the meter protection, it must be to Dominion Energy requirements.