SCC

The Virginia State Corporation Commission (SCC) is responsible for verifying the need, approving the route and structures and reviewing the environmental impact of certain transmission lines in Virginia.

On October 11, 2024, Dominion Energy filed its application with the SCC. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2024-00179 in the "Search Cases" section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments. Please note, the mailbox may not be available until a scheduling order is issued, typically several weeks after an application is filed.

Application

On November 6, 2024, the SCC issued an Order for Notice and Hearing.

Procedural Schedule

  • November 29, 2024 – Landowner Notice, Publication Deadline, and Government Official Notice
  • December 13, 2024 – Proof of Notice and Certificate of Mailing deadline
  • January 15, 2025 – Notice of Participation deadline
  • January 15, 2025 – Respondent Testimony due
  • January 22, 2025 – Staff Report due
  • February 5, 2025 – Company Rebuttal Testimony due
  • February 5, 2025 – Public witness signup deadline
  • February 5, 2025 – Any interested person may submit comments on the Application (on or before)
  • February 12, 2025 – Telephonic Hearing for Public Witness Testimony (10:00 a.m.)
  • February 12, 2025 – In-Person Public Evidentiary Hearing (10:00 a.m.)