Project Updates

April 12, 2024

200 South; West Temple to 200 West

On Tuesday, April 16, our crews will begin installing plastic pipe in the south shoulder of 200 South between West Temple and 200 West. This is expected to take approximately three weeks to complete.

  • During this work, there will be NO on-street parking available along the south side of 200 South on this block.
  • Business, parking garage, and sidewalk access will be maintained.

200 West; 200 South to Pierpont Avenue

For three more weeks, Whitaker will continue installing the new gas pipeline along 200 West.

  • During construction on 200 West, our crews will maintain one lane of traffic in both the north and southbound directions.
  • Westbound traffic on 200 South through this intersection will be pushed to the north side of the road. Eastbound traffic MUST turn right onto 200 West.
  • There will be NO LEFT TURNS off of 200 South onto southbound 200 West.
  • There will be NO on-street parking along both sides of this block.

West Temple/200 South Intersection Closure

The West Temple/200 South intersection is CLOSED through early-May while our contractor crosses the intersection with the new pipe.

  • Right turns are permitted through the intersection in all directions at all times, but please note, the east-to-southbound right turn is available for Holiday Inn Express customer access ONLY.
  • Eastbound 200 South, from 200 West to West Temple, is open to business and parking garage access ONLY.
  • Suggested alternate detour routes include 200 West, Main Street, and State Street to 300 South and South Temple.

Work will typically take place between the hours of 7 a.m. and 7 p.m., Monday through Friday. Weekend and night work may take place on occasion if needed.

  • Pedestrian routes and crossings will remain unobstructed during this work.
  • Nearby residents and businesses can expect increased noise, dust, and vibration associated with construction.

Please note, construction schedules are always subject to change due to weather or other unforeseen circumstances.

If you have any questions or concerns, please reach out to our team anytime.

Salt Lake City System Improvement - BL 7 (200 South) Project Map

Please note that the project map represented here is subject to change.

Project Information

Need for the project: These improvements are necessary for Dominion Energy Utah to keep pace with growing customer demand for natural gas, maintain overall system integrity and continue providing safe and reliable service.

Location: This section of natural gas pipeline is located in downtown Salt Lake City. Work will take place at all intersections of 200 South from 400 West to 200 South. To minimize the inconvenience to businesses and residences, Dominion Energy is working in conjunction with Salt Lake City's 200 South corridor project.

Construction Schedule: We are committed to completing this work as quickly and with as little inconvenience to local businesses and residents as possible. Crews are scheduled to start in Spring 2023. To expedite construction, multiple crews may be working simultaneously at various locations and may perform nighttime and weekend work. No interruption to residents' natural gas service is anticipated during this project. Work will be completed in two phases. Phase I will start in Spring 2022 and end in Winter 2022. Phase II will start in Spring 2023 and will continue into 2024.

To provide room for crews and equipment, some temporary lane restrictions, especially at intersections, will be necessary. Please drive carefully and obey all signs and flaggers. To avoid congestion in construction zones, motorists are advised to use alternate routes when possible and to allow plenty of travel time to get where they're going. At all times, our crews will make every effort to maintain access to businesses and driveways in construction zones.

We appreciate your patience.

Dominion Energy is committed to completing this project safely and on schedule while minimizing as much as possible any inconvenience to local businesses and residents. To accomplish this, some work may be performed at night and on weekends. This will reduce impacts on morning and evening commutes. We will adhere to all county noise-reduction ordinances.

Construction Zones

For pipe buried beneath streets or highways, construction may require intermittent closures of one or more lanes of traffic. Driveways also may be occasionally blocked by excavation work, otherwise they will be plated to maintain access during business hours and at night and on weekends.

Before construction starts in front of any home or business, a representative will contact the owner or resident to discuss options for maintaining driveway access. Signs notifying the public that businesses remain open during construction are available.

To finish construction on schedule and as quickly as possible, the project is divided into sections, or "spreads." This allows multiple crews to work simultaneously at different locations. Work zones can range from a single intersection to several blocks long. At any one location the amount of time to cut pavement, install new pipe and replace asphalt can range from several days to several weeks.

The public can do its part to ensure construction proceeds safely and on time by finding alternative routes, driving carefully in construction zones and keeping children away from construction sites.

Dominion Energy works closely with city and state transportation officials to ensure safety and minimize inconvenience to drivers and pedestrians. However, for public safety it may be necessary to temporarily close streets and sidewalks or restrict vehicle and pedestrian traffic. As mentioned, driveways may occasionally be blocked by excavation work. We will make every effort to keep these inconveniences as brief as possible. Your patience is appreciated.

If you have questions or concerns, do not hesitate to contact us.

Steps During Construction

Following are brief descriptions of the steps involved in pipeline removal and construction:

  • Locate buried utilities - The area below city streets can be a maze of underground utilities. To avoid damaging these facilities, a procedure known as potholing is used prior to trenching to identify the exact vertical and horizontal location of existing infrastructure, including the pipeline to be replaced.
  • Move existing utilities - Before trenching (see next step), all water and natural gas service lines that cross the existing pipe will be moved to a lower depth. This will minimize the risk of interrupting water- or gas-service to individual homes or businesses once actual construction begins.
  • Dig trench - After the pipe has been located and purged of gas and service lines in the trench zone moved, the pavement above the existing pipe is cut and removed. Then equipment is brought in to dig the trench. The depth of the natural gas pipeline trench will be determined by the location of the existing pipe and other utilities. As the trench is dug, the soil is loaded into trucks and hauled away for disposal in a designated landfill.
  • Remove old pipe - Sections of pipe to be removed are cut into lengths, lifted from the trench, loaded onto trucks and hauled away for proper disposal.
  • Deliver and "string" new pipe - New pipe is manufactured and inspected to ensure it meets industry and federal safety standards. Pipe sections are then delivered by truck to the construction site where they are placed end-to-end (or "strung") on skids adjacent to the trench. If necessary, a hydraulic machine bends pipe sections to fit around obstacles or conform to the direction of the trench.
  • Weld new pipe together and coat - Welding crews join the sections of pipe together into a continuous length. Each welded joint is visually inspected, x-rayed and then coated for protection.
  • Lower pipe into trench - Using one or more tractors, crews lift and then carefully lower the welded sections of pipe into the trench. Final welds are made to "tie-in" any unconnected sections.
  • Backfill trench - Under streets, in place of the removed soil, a mixture known as "flowable fill" is used to backfill the trench. In other areas, the original soil is replaced.
  • Pressure test new pipe - After it's buried and before it's put into service, the entire length of new pipe is hydrostatically tested to ensure the integrity of the system. This is done by filling the pipe with water, pressurizing the system above its maximum operating conditions and holding the pressure for a specified time. The pipe is drained, cleaned and dried before put into service.
  • Clean-up and restore ROW - The final step is to repair the surface over the trench. If necessary, fences or sod may also be replaced.
  • Directional bore - At some busy intersections, most water crossings and under major roads, instead of trenching, crews will install pipe by boring horizontally underneath the road, stream or canal. The boring machine drills a hole from one side of the road or stream. Pipe is strung on the other side and then pulled back through hole.

We take safety seriously. Since its founding in 1929, our company and its affiliates have engaged in every phase of natural gas service, from production and gathering to transportation and distribution. During that time, while delivering the clean and efficient natural gas our customers rely on daily for their comfort and livelihood, we have earned an enviable record for safety and reliability.

Frequently Asked Questions

At Dominion Energy, we are committed to providing safe, reliable natural gas service at the lowest possible cost.

In recent years, as part of our continuing efforts to meet growing demand for natural gas while improving overall system integrity, we have begun replacing vital sections of our underground pipeline system serving the Wasatch Front. In most cases we are replacing older pipe with newer, stronger and larger diameter pipe.

These new pipelines carry more supplies, enabling us to better serve the growing number of new homes and businesses in Utah.

They also enhance safety and reliability by making our system easier to monitor and maintain. Some of the older sections of our system have pipe in varying diameters, ranging from six to 20 inches. Replacing these with pipe of the same diameter makes them accessible to "smart tools. These tools -- commonly known as "pigs" -- use MRI technology to inspect the pipe interior, making it possible to detect and correct potential problems before they occur.

No. Redundancies in our system should make it possible to replace the existing pipeline without interrupting service to any customers.

If your property is on or adjacent to the right-of-way, you will receive prior notification by mail alerting you to construction. We work closely with residents and city officials to minimize potential impacts on residents' property. If we do need to access its legal right-of-way to work on or near your property, the company will make reasonable efforts to ensure the landscape is returned as closely as possible to its previous state. This does not include replacement, repair or compensation for unauthorized structures, plants, objects and etc. currently located within the right-of-way.

Residents can make the process easier by making sure that items such as large, deep-rooted trees, concrete slabs, sheds, fences or other structures do not encroach upon our right-of-way. These items not only violate right-of-way policy but also pose a safety hazard and may hinder our ability to reach our pipeline in case of emergency or to perform necessary maintenance.

For more information about what is and is not allowed on pipeline rights-of-way, request a company brochure by contacting a representative at 801-324-3149 or view our brochure.

Construction may require temporary lane closures and/or detours. During construction, we strive to maintain traffic in both directions on city streets at all times, however temporary lane restrictions can be expected.

Private driveways and access to side streets and business parking lots may also occasionally be temporarily blocked by excavation work. When not in use, open trenches will be plated to maintain access during business hours, at night and on weekends.

Any changes in traffic or access will be kept to a minimum and will be as brief as possible.

Before construction starts in front of your home or business, a company representative will contact you to discuss where you would like access maintained. Signs notifying the public that businesses are open during construction will be made available for those who request them.

Residents can reduce the risk of accidents by driving carefully in construction zones and keeping children away from the construction site. We work closely with city and state transportation officials to ensure safety and minimize inconvenience to drivers and pedestrians during construction.

This project has a dedicated email and 24/7 hotline for any questions or concerns. Please send us an email email or call the hotline at 385-557-2585