End of 2025
Project completion target
Early 2025
Begin Phase 4 Construction
Fall 2024
Begin Phase 3 Construction
Summer 2024
Begin Phase 2 construction
June 2024
Unity Substation Conditional Use Permit approval by Lunenburg County
Early 2024
Begin Phase 1 Construction
Early 2024
Begin construction
June 14, 2023
SCC issued final order. Visit our legal page to learn more about the approved routes.
Legal Page
Legal Page
October 6, 2022
UPDATED: Submitted application with the Virginia State Corporation Commission (SCC)
Summer 2022
Host public community meetings - June 1, June 6, June 7, and July 20
Visit our meetings page
Visit our meetings page
April 2022
Notify public of the project