The Company shall submit quarterly construction status updates regarding the Rebuild Project to the Director of the Commission's Division of Public Utility Regulation until the Rebuild Project is completed or until further order of the Commission.
The Company shall post each quarterly construction status update on the Company's website: www.DominionEnergy.com/shreve.
The Company shall post its Construction Timeline on the website noted in Ordering Paragraph (4). The Company shall update this Construction Timeline as needed to maintain accuracy.