The Virginia State Corporation Commission (SCC) is responsible for verifying the need, determining the route and reviewing the environmental impact of certain transmission lines in Virginia.

On August 3, 2022, Dominion Energy filed its application with the SCC. On April 24, 2023, the SCC issued its Final Order approving the project for construction. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2022-00123 in the "Search Cases" section. In addition, interested parties may comment directly to the SCC by sending an email to sccinfo@scc.virginia.gov.

To learn more about this process, view our SCC process map.

SCC Timeline (Updated as of April 26, 2023):

  • November 18, 2022 – Notices of Participation deadline
  • December 16, 2022 – Respondent Testimony deadline
  • February 10, 2023 – Deadline for Public Comments
  • February 10, 2023 – Deadline for public witnesses to indicate desire to testify
  • February 14, 2023 – Public Witness Hearing, 10:00 a.m.
  • February 15, 2023 – Evidentiary Hearing, 10:00 a.m., 2nd floor courtroom SCC
  • April 24, 2023 – SCC Final Order Issued