Wateree -Hopkins Project

The project will rebuild an 18-mile transmission line to improve Richland County’s reliability and capacity.


Project Details

Dominion Energy will upgrade an existing electric transmission line in eastern Richland County. The project will replace aging poles, wires and equipment to improve reliability, strengthen the line during severe weather and meet growing energy needs.

Benefits

What To Expect

Project Description

Dominion Energy and its contractors will replace approximately 18 miles of 230-kilovolt (kV) wooden structures with self-supporting galvanized steel poles. The new line will be designed to meet all modern electric codes as well as provide additional reliability for our customers.
 
Letters will be sent out to impacted property owners along the route as we progress through its construction.

Location

The project will begin at the substation near Wateree Generating Station off U.S. Highway 601 in Eastover. From there, it will follow the existing right of way west and northwest for approximately 18 miles to the vicinity of the Westinghouse Electric fuel fabrication facility near Hopkins. Tree trimming and removals will also be required along the existing right of way. 

Timeline

Engineering design and environmental permitting began in summer 2026. Transmission line construction will begin in early 2027 and continue until the end of the year. In addition to weekdays and normal work hours, weekend work hours may be necessary to meet critical project schedules.

Líneas eléctricas 101 — Zona de aprendizaje

Aprenda cómo funciona la red eléctrica, así como nuestros procesos para construir y mantener las líneas de transmisión eléctrica.
Descubre más sobre tus líneas cta btn