How can we help you?
McLean Partial Rebuild
230 kV Electric Transmission Project
This project proposes to rebuild a part of an existing 230 kV transmission line. All work will occur in the existing right of way.
Project Details
- The project will replace aging equipment, especially foundations of structures damaged by erosion from the Pimmit Run Stream.
- Located in Fairfax County in the Dranesville District, the section of the line being replaced is about two and a half miles from just east of Route 267 to just south of the Potomac School.
- The lines will continue to be 230 kilovolts (kV).
- This project will require approval from the Virginia State Corporation Commission (SCC).
- Public outreach will begin in the fall of 2026. The project team plans to file the application with the SCC in November 2026.
- Construction is targeted to begin in summer 2028, and complete by summer 2029.
- There will not be disruption to your electrical service due to this work.
Maps and Simulations
Project Simulations
Community Engagement
Upcoming Meetings
- In-person Open House (no presentation)
Tuesday, October 6, 2026
5:30 p.m.–7:30 p.m.
DoubleTree by Hilton McLean
1960 Chain Bridge Road
McLean, VA 22101
- Virtual Community Meeting (with presentation and Q&A)
Tuesday, October 13, 2026
12:00 p.m.
Meeting Link
Project Communications
What to Expect
Project Timeline
2026
Late Summer 2026
Public announcement
October 2026
In-person open house and virtual community meetings
November 2026
Target filing with Virginia State Corporation Commission (SCC)
2027
Fall 2027
Anticipated SCC approval
2028
Early 2028
Detailed design
Summer 2028
Construction targeted to begin
2029
Summer 2029
Construction scheduled to complete
Legal
The Virginia State Corporation Commission (SCC) has regulatory authority over all energy providers in Virginia. Among other responsibilities, the SCC validates the need for a proposed line and approves the route and structures. In reviewing a proposed project, the SCC must consider whether potential impacts on scenic assets, historic districts and the environment have been reasonably minimized.