Chesterfield-Lanexa
230 kV Electric Transmission Rebuild
Project Details
Dominion Energy is proposing to rebuild a double-circuit 230 kilovolt (kV) electric transmission line between our Chesterfield and Lanexa Substations. The structures along this 28-mile corridor have been in operation for more than five decades and will be rebuilt to maintain reliable electric service.
The SCC issued its Final Order approving the project on March 2, 2026.
Community Engagement
To learn more about this project, we invite you to join us for an in-person community meeting on August 19 and/or a virtual community meeting on August 20. You will have the opportunity to learn details about the project and have your questions answered by our project team. If you are unable to attend the virtual meeting, a recording will be available on the project website.
Documents
Timeline
2029
August 2029
Construction complete
2027
March 2027
Construction begins
2026
Summer 2026
Anticipated SCC ruling
2025
Fall 2025
SCC filing
August 2025
Community meetings
July 2025
Project announcement
The Virginia State Corporation Commission (SCC) is responsible for verifying the need, determining the route, and reviewing the environmental impact of certain transmission lines in Virginia. Key filing documents will also be available on this page.
On September 10, 2025, Dominion Energy filed its application with the SCC. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2025-00154 in the Search Cases section. In addition, interested parties may visit the SCC Case Comments page where individual mailboxes are available for each case accepting public comments. Please note, the mailbox may not be available until a scheduling order is issued, typically several weeks after an application is filed. The SCC issued its Final Order approving the project on March 2, 2026.
To learn more about this process, view our SCC process map.
SCC Documents
| Application Volume 1 and 2 |
|---|
| Application Volume Part 1, Part 2 |
| Application Volume 2, Part 2, Part 3, Part 4, Part 5, Part 6 |
SCC Timeline
- December 12, 2025 - Landowners Notice, Newspaper Publication Deadline, Government Officials Notice (to include Attorneys)
- January 5, 2026 - Proof of Notice & Service and Certificate of Mailing Deadline
- January 5, 2026 - Deadline for interested person(s) to file comments on the Application
- January 5, 2026 - Notice of Participation Deadline
- January 5, 2026 - Deadline for any interested person(s) to file a request to convene a hearing
- January 16, 2026 - Staff Report Due
- January 30, 2026 - Company to file response to Staff Report and any requests for hearing and comments