Tributary 230 kV Electric Transmission Project

Support growing energy demands in Spotsylvania County.
Lineworker in front of Dominion Energy truck

To support growing energy demands in Spotsylvania County, the Tributary 230 kV Electric Transmission Project is proposing a new substation and double circuit 230 kV electric transmission line.

This new infrastructure will allow us to meet the growing energy needs, continue reliable electric service, and maintain compliance with federal reliability standards.

Benefits

  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Strengthens area reliability
  • Strengthens operational flexibility 

Documents

Maps

Proyecto de Transmisión Eléctrica de 230 kV de Tributary

Para apoyar la creciente demanda de energía en el condado de Spotsylvania, Dominion Energy propone una nueva subestación y una línea de transmisión eléctrica de 230 kV de doble circuito para conectar la nueva subestación a nuestra red de transmisión eléctrica existente.

Esta nueva infraestructura nos permitirá satisfacer las crecientes necesidades energéticas, continuar con un servicio eléctrico fiable y mantener el cumplimiento de las normas federales de fiabilidad.

Beneficios

  • Cumple con las normas obligatorias para garantizar la seguridad y la fiabilidad y para satisfacer las necesidades futuras
  • Refuerza la fiabilidad de la zona
  • Refuerza la flexibilidad operativa

Cronograma

  • Principios del verano de 2024 - Anuncio del proyecto
  • Verano de 2024 - Divulgación al público
  • Principios del otoño de 2024 - Se presenta la solicitud ante la Comisión Estatal de Sociedades (State Corporation Commission, SCC) de Virginia
  • Verano de 2025 - Fallo previsto de la SCC
  • 2025–verano de 2026 - Tramitación de permisos, finalización de la ingeniería, divulgación previa a la construcción
  • Verano de 2026 - Comienza la construcción
  • Principios de 2027 - Finaliza la construcción, comienza la restauración
Documentos
  • Hoja informativa del proyecto
  • Mapa del área de estudio del proyecto
  • Carta de anuncio del proyecto

Contáctenos

Llámenos de lunes a viernes, de 8 a.m. a 5 p.m.

888-291-0190

Envíenos un correo electrónico a

powerline@dominionenergy.com

The Virginia State Corporation Commission (SCC) has regulatory authority over all energy providers in Virginia. Among other responsibilities, the SCC validates the need for a proposed line and approves the route and structures. In reviewing a proposed project, the SCC must consider whether potential impacts on scenic assets, historic districts and the environment have been reasonably minimized. On October 1, 2024, Dominion Energy filed its application with the SCC.

SCC Application Filing

The SCC issued its Final Order approving the project on June 30, 2024. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2024-00181 in the "Search Cases" section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments.

Due to upcoming economic development in the area, we are working with Rappahannock Electric Cooperative (REC) to plan for new electric infrastructure. The Tributary project proposes a new substation and double circuit 230 kV electric transmission line to maintain federal reliability rules and keep the grid operating efficiently.

Dominion Energy has an obligation to serve and maintain reliability for all customers. Entities such as PJM – which operates the electric grid in 13 states – and NERC, North American Electric Reliability Corporation, enforce standards to ensure reliability and the prudency of investments by utility companies like Dominion Energy.

Our project team will focus on public outreach in summer 2024 to ensure all interested community members are aware of the project and have an opportunity to share feedback with our team as we continue the planning process. We intend to file an application with the SCC in fall 2024.

The SCC is the regulatory body with jurisdiction over transmission lines at or above 138 kilovolts (kV). Since this project is proposing to build a new double circuit 230 kV transmission line, it meets the criteria to be reviewed by the SCC. Dominion Energy intends to file an application in early fall 2024.

Although the SCC is the primary agency reviewing and ultimately approving the project, there may be additional permits needed from local, state, and federal agencies.

We want to hear your feedback. The purpose of our public engagement is to share, listen and learn from our community members. The SCC also considers public input in its review process. There are multiple ways to share your feedback with our team:

Interested community members are welcome to request a separate meeting with our team. Whether you have a scheduling conflict during the community meeting dates, would like to discuss your property specifically, or would like to continue a discussion with our team following a community meeting, we are available for additional meetings by request.

Members of the community may be Rappahannock Electric Cooperative (REC) customers. However, Dominion Energy provides electric transmission service to REC, which in turn delivers electric distribution service to your home or business. The Tributary project proposes a new electric transmission line in your area that will source power to REC.

Thursday, June 13, 2024
5–7 p.m.
Massaponax High School

View content shared at community meeting:

 

Tuesday, July 30, 2024

5–7 p.m.
Massaponax High School

 

Couldn't make the meetings? No problem.

Interested community members are welcome to request a separate meeting with our team. Whether you have a scheduling conflict during the community meeting dates, would like to discuss your property specifically, or would like to continue a discussion with our team following a community meeting, we are available for additional meetings by request.

Upcoming

Early 2027
Construction Complete, Restoration Begins
Summer 2026
Construction To Begin
2025 - Summer 2026
Permitting, Finalize engineering, Pre-construction outreach

2025

Summer 2025
Anticipated SCC Ruling

2024

Early Fall 2024
File application with the Virginia State Corporation Commission (SCC)
Summer 2024
Public Outreach
Early Summer 2024
Project Announcement

Construction-Related Impacts

Low impact symbol

Service Interruption

Your electric service is not expected to be impacted by this project.

MapChat by ERM - Our Interactive Mapping Tool

View routes in detail cta btn

Powerlines 101 - Learning Zone

Learn how the energy grid works; along with our processes to build and maintain electric transmission lines.
Discover about your lines cta btn