Castlewood Project Site

Dominion Energy owns and operates a large materials and metering service center on Castlewood Road in Richmond, Virginia. The facility includes an equipment repair shop, material recycling, transportation, warehousing and rubber testing services. Located along Grindall Creek, the operational facility is working to update the stormwater drainage system to improve the quality of runoff into the nearby waterway.

Dominion Energy is upgrading the Castlewood Road facility for business and environmental stewardship purposes. Included in this upgrade is a new covered storage building for tanker trucks as well as an underground stormwater system designed to decrease environmental impact and enhance operational compliance.

The first phase of this project began in April 2023 and is expected to be completed in April 2024. This phase includes a new stormwater management system, tank storage building and lot resurfacing.

This project has received Pre-Certification under the United States Green Building Council (USGBC) Sustainable Sites Initiative (SITES). It is the first and only industrial site to receive this pre-certification.

Project Benefits

The local water ecosystem will benefit from the facility's upgrade. A long-term monitoring and maintenance plan is being developed by Dominion Energy and Blueline Environmental. A section of Grindall Creek will be restored using natural materials while native plant species are reintroduced. This will not only support the natural ecosystem in the creek but will increase the structural stability of the creek and its embankments. This project is being conducted in accordance with the current science and practice of restoration of aquatic ecosystems and is permitted by both State and Federal agencies.

Castlewood Project Site

Project Timeline

Phase Event
Phase 1.1
April 2023 ‐ April 2024
Covered tanker storage, new underground stormwater system, lot resurfacing
Phase 1.2
May 2024 – December 2024
Tank and containment upgrades, new underground stormwater system, lot resurfacing, bushing rack redesign
Stream Restoration
Q1 2025
Restore stream
Phase 2.0
2025
Lot resurfacing
Phase 3.0
2026
Lot resurfacing
Phase 4.0
2027
Lot resurfacing