Cannon Branch-Winters Branch
230 kV Line Extension
Project Overview
Cannon Branch-Winters Branch Line Extension
This project involves extending an existing 230 kV electric transmission line by building a new section of the line between the existing Cannon Branch Substation in the City of Manassas and Winters Branch Substation in Prince William County, Virginia.
The existing portions of this 230 kV electric transmission line are also being rebuilt under a related project. Please visit our Clifton-Winters Branch project page for additional information on this related project. Together, these projects will result in a full transmission line running from our Clifton Substation to our Winters Branch Substation in Prince William County, near Prince William Parkway.
Benefits
- This project helps maintain federal reliability standards and electric reliability for the community.
Timeline
- June 2021 – Notified public of project
- June 2022– SCC issued final order approving project
- Early 2023 – Began substation construction activities
- Early 2024 – Continue forestry and construction activities
Legal
SCC Applications
The Virginia State Corporation Commission (SCC) has regulatory authority over all energy providers in Virginia. Among other responsibilities, the SCC validates the need for a proposed line and approves the route and structures. In reviewing a proposed project, the SCC must consider whether potential impacts on scenic assets, historic districts and the environment have been reasonably minimized.
On 12/16/21, Dominion Energy filed its application with the SCC. The SCC issued its Final Order approving the project on 6/24/22. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2021-00291 in the " Search Cases " section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments.
Meetings
Virtual Community Meetings
Date: Thursday, December 9, 2021 - Time: 6:00 p.m.
Our subject matter experts reviewed the project, discussed the construction process, and answered questions
Missed the meeting? View the recorded video.
Timeline
2024
Early 2024
Continue forestry and construction activities
2023
Early 2023
Began substation construction activities
2022
Fall 2022
Conducted environmental surveys and wetlands delineations
2021
December 2021
Filed application with SCC
December
Held virtual community meeting
June
Notified public of project