Blackwell Road

230 kV Transmission Line and Substation

Project Overview

To serve a proposed data center customer located near the corner of Blackwell Road and Lee Highway in the Town of Warrenton

Economic growth in Fauquier County has resulted in increased electrical demand. To support this demand, there is a need for new electrical infrastructure. We are pleased to propose an updated solution to serve a potential data center coming to the Town of Warrenton, and to maintain reliable and secure service to the area. This updated solution includes a substation, off-site from the data center property. It will serve the data center with in-road, underground distribution lines. We are evaluating two potential sites for the substation. Both are close to the existing transmission line south of the Town of Warrenton. Please refer to our updated routing maps and virtual open house for more information.

View new routing maps for our updated proposed solution on the Maps Page.

Survey Work In Progress

In the coming days or weeks, you may see Dominion Energy personnel performing survey work in the Blackwell Road Project area. Please note that this is a normal part of our due diligence process, and does not indicate finalized route plans or that construction is beginning. Check back here for updates on our plans and progress. - Updated March 27, 2023

Virtual Open House

Please visit our virtual open house where you can engage in an interactive experience, view the latest preliminary routing options, learn more about the project, and provide your feedback.

Benefits

  • Will provide secure and reliable service to not only the customer substation site, but the broader area as well

Timeline

  • April 2022 – Notified public of the project
  • April 2022 – Convened first meeting of Project Participation Group
  • June 2022 – Hosted second meeting Project Participation Group and two public Community Meetings
  • Summer 2022 – Continued meetings with area residents and organizations
  • November 2022 - Proposed updated electrical solution with an off-site substation
  • TBD – File project with the State Corporation Commission (SCC)

Construction Related Impacts

Service Interruption

Your electric service is not expected to be impacted by this project.
Calendar symbol

Equipment Lifespan

40 Years - The time the updated equipment will last once in service.

Maps

Below, you will find updated exhibits for a new substation located off-site from the data center property.

  • Option 1 features a short transmission line span (approximately 0.5 miles) to a substation off of Falmouth Street. From there, in-road, underground distribution lines go to the data center site (approximately 3 miles).
  • Option 2 features a substation closer to the existing transmission line. Underground distribution lines go to the data center site from there.

These proposed routes are still under evaluation and are subject to change.


November 2022

Substation (Off-site) Routing Options


June 2022

Preliminary routing options


May 2022

Environmental map set.
Due to the file size of the maps, they may take some time to open on your computer or mobile device.

FAQs

What are the current solutions proposed by the project team?

The updated proposed solution includes an off-site substation location to serve the data center customer at Blackwell Road. Two parcels are being evaluated as potential sites for a substation. One parcel is off of Falmouth Street, requiring a short transmission line span of approximately 0.5 miles. The other parcel under consideration is closer to the existing transmission line, which may reduce the need for transmission line structures while adding more underground distribution line distance.

Are the overhead Warrenton and Wheeler transmission routes presented by Dominion during Summer 2022 no longer under consideration? Will a substation still be built at the intersection of Blackwell Road and Lee Highway?

No, the proposed routes presented by Dominion Energy from the Wheeler Substation to the proposed Blackwell Substation, as well as the routes from the Warrenton Substation to the
proposed Blackwell Substation, are no longer under consideration. Dominion Energy is no longer proposing an on-site substation to serve the customer at the intersection of Blackwell Road and Lee Highway.

What is the difference between electric transmission and electric distribution?

There are two types of lines that carry power from the generation source to your home and business –electric transmission and electric distribution lines. The lines look different and serve different functions. Bulk electricity is generated at a power station and transported most efficiently via high voltage transmission lines to a local substation. At the substation, voltage is lowered and electricity can be dispatched through a maze of distribution lines to power an entire community. Please visit our Powerline 101 site for a video that helps illustrate the differences between transmission and distribution voltages and the unique requirements of each.

Would the proposed lines be overhead or underground?

All of the solutions currently being evaluated involve predominantly underground construction of distribution circuits. Two parcels are being evaluated as potential sites for a substation. One parcel is off of Falmouth Street, requiring a short, overhead transmission line span of approximately 0.5 miles. The other parcel under consideration is closer to the existing transmission line, which may reduce the need for transmission line structures while adding more underground distribution line distance.

How are the routes determined?

Routes for any new linear facilities are developed in sequential phases beginning with a desktop review of existing features and constraints, such as cultural or environmentally sensitive or protected areas, and other land uses such as residences, schools, and parks. Routing is an iterative process that first considers existing opportunities for co-locating along existing corridors, such as roadways or other linear easements. The team will explore any electrically viable option, then narrow down to the preferred options. The evaluation will include a quantitative analysis based on our routing criteria as well as other factors. Dominion Energy relies on input from the public, regulatory agencies and other key stakeholders to determine an appropriate solution that will meet the need of the project while minimizing environmental impacts.

How would the lines be constructed underground (boring, open ditch, etc.)?

Right now, the newly proposed electrical approach is still in its preliminary stage. Dominion Energy’s electric distribution team is still evaluating the in-road, underground construction method. We will continue to work with the community to share construction and related updates at upcoming community meetings and on our website, www.dominionenergy.com/blackwellroad.

When would this work begin?

Work will only commence once all state and local permits are in place. Based on our current plans, construction would start sometime in 2024. Additional clarity can be provided as we progress through the permitting process.

The proposed solutions first presented in the summer provided more time for community review, prior to submitting to the SCC. Why do these proposals have a shorter timeframe?

Dominion Energy sets the SCC filing date. We pushed our original filing date from the fall of 2022 to the first quarter of 2023 in order to re-evaluate a new approach. We are still planning robust public engagement, including virtual and in-person meetings, sharing revised maps and continuing our ongoing engagement with the community and our partners at the Town of Warrenton and Fauquier County. If we are not ready to submit a filing in the first quarter of 2023, we will consider moving the date out to a time when we have completed our reviews and community engagement.

What plan is in place to minimize the impact of the work on the Blackwell Road community?

In-road construction would typically require a 30'–40' easement. Traffic would be rerouted from one side of the road first, and then the other to complete the work. Dominion Energy works closely with VDOT and local partners prior to detouring or closing roads to the public. These detours and closures are communicated by Dominion Energy to area residents in advance of project-related work. Dominion Energy is committed to working with town and county partners to minimize delays and related construction inconveniences. We will adhere to town ordinances and work within our permitted hours and other restrictions. We will maintain our community presence as well as our website and powerline communications portal throughout construction.

Does Dominion have a preferred route so far?

Dominion has collected a significant amount of input from residents and continues this effort to better understand the many different local constraints that may not have been perceptible using only desktop analysis. At this time, all routes published so far are preliminary and subject to change; however, Dominion Energy prefers the Falmouth site because of the size of the property and access into and out of the site. That said, we will continue to work with our partners at the county level to evaluate what is possible with regard to the county-owned parcel.

Why is a route up the 15/29 corridor not being considered?

We are continuing to explore the possibility of an underground easement along the 15/29 corridor with VDOT. However, there are several known considerations in that area that may preclude us from burying underground lines there. There is a known contamination issue in the Frytown community; drainfield issues; and space constraints for access roads. We will continue to coordinate with VDOT to see if there are alternate options in that area to consider.

How are the proposed routes determined and what potential issues (existing structures and uses, private property, environmental, community/common property, etc.) are taken into account when a route is designated as a proposed route?

Routing is an iterative process that first considers existing opportunities for co-locating along existing corridors, such as roadways or other linear easements. The team will explore any electrically viable option then narrow down to the preferred routing options by assessing impacts to existing features such as cultural or environmentally sensitive or protected areas, and other land uses such as residences. The evaluation will include a quantitative analysis based on our routing criteria as well as other factors.

Have any of your engineers/planners actually walked the track you have laid out to assess what is actually located on these routes? Both above and below ground?

For all of the routing scenarios being evaluated, the lines will predominantly be buried underground, under public roadways. There will likely be a few overhead transmission structures and spans closest to the existing overhead lines behind Dominion Energy’s existing Warrenton office on Meetze Rd. We will continue to work with our town and county partners as well as members of the community to better understand local priorities and constraints within the study area. As we have been doing for months, we will meet with private property owners along the different routes as requested.

What will these proposed power lines look like? What kinds of towers? Height? Number of lines?

The new electrical solutions under consideration are primarily underground circuits that will be constructed in-road. Engineering for the short, 0.5 mile span of overhead transmission is still being developed. Typical 230kV transmission line construction is dependent upon right of way requirements. They can be constructed of weathering steel, which turns dark brown over time or galvanized steel, which is a pale, dull gray. Examples of galvanized steel, double-circuit monopoles carrying 230 kV lines can be seen today off Meetze Road in Warrenton, behind the local Dominion office, and extending to the Warrenton Substation, which sits next to the Central Sports Complex. These structures vary in height, between 85-130' tall, and each structure holds a total of 8 wires—two sets of 3-phase circuits, plus lightning arrestors at the very top.

How much right of way is required for in-road construction?

In-road, underground distribution would require a 30'– 40' easement.

Will VDOT inform the residents in advance of road closures for underground construction?

In-road construction would require a 30'– 40' easement. Traffic would be rerouted from one side of the road, and then the other to complete. Dominion Energy works closely with VDOT or the locality prior to detouring or closing roads to the public. These detours and closures are communicated by Dominion Energy to area residents in advance of project-related work.

How much capacity will be available at the substation?

The new substation will have enough capacity to serve the data center customer and other electricity users across the community. Having a second source of power provides greater reliability for the community, and improved operational flexibility when needed during outages.

Could Dominion upgrade to 500 kV in the future?

We have no plans to do so at this time, however, we are legally obligated to serve our customers when requests are made.

What routes or portions of routes will require SCC approval?

Any transmission structures require SCC review; the 0.5 mile span from the Falmouth property would require SCC review. Any distribution lines and the substation are subject to town permitting.

Is the SCC filing date conditioned by the customer?

The customer sets a target in-service date.

The town has authority over underground installation and substation construction. Will any portion of the transmission line come into the town?

Yes, the 0.5 mile transmission line from Falmouth would tap into existing overhead lines, crossing from county jurisdiction to town jurisdiction on the west side of Rt. 29, as it enters the Falmouth substation.

Will Dominion Energy or the customer file the Special Use Permit (SUP) for the substation?

The substation SUP will be filed by Dominion Energy.

What will happen if the customer’s SUP is denied?

This project is being driven by a load request submitted by the customer. If the customer’s SUP is denied, this project is no longer needed.

Who will pay for the infrastructure?

The customer will pay for the underground distribution portion of the project. The substation will be paid by customers across the Commonwealth of Virginia.

Who pays for the liability related to property damage, etc.?

Dominion Energy is fully responsible for the construction, operations and maintenance of our facilities. During construction, Dominion Energy has a hotline to submit claims for property damage.

Are substations only required for data centers?

Substations are designed to lower transmission line voltage to distribution level voltage to power homes, businesses, schools, hospitals, etc. They are not only required for data centers.

Meetings

Virtual Community Meeting with Area Homeowner’s Associations

Recorded June 15th, 2022

Timeline

2022

November 2022
Proposed updated electrical solution with an off-site substation

2023

TBD
File project with the State Corporation Commission (SCC)
Summer 2022
Continued meetings with area residents and organizations
June 2022
Hosted second meeting of Project Participation Group and two public Community Meetings
Please visit our meetings page for information on these events
April 2022
Notified public of the project
April 2022
Convened first meeting of Project Participant Group