Important Construction Update

  • Spring 2023 – The energizing of the new Idylwood-Tysons line, originally scheduled for late 2022 is now delayed due to repeated faults during cable testing.

Benefits

  • Enable Dominion Energy to continue to provide reliable power to the area.

Timeline (View Full Timeline)

  • May 2020 - Postcard mailed to the community announcing permit approvals and start of construction
  • October 15, 2019 - Construction Informational Open House (5:30 pm - 7:30 pm) Kilmer Middle School, 8100 Wolftrap Road, Vienna, VA 22182
  • September 5, 2018 - The SCC issued its final order approving the Idylwood-Tysons transmission project.
  • July 26, 2018 - The SCC Hearing Examiner’s Report was issued in response to the proposed project.

Contact Us

Call us M - F, 8am - 5pm

(888) 291-0190

Updates

View portal for weekly updates

Overview & Project Description

Community Engagement

At Dominion Energy, we are committed to keeping our neighbors informed about energy needs where they live and work. As we continue to analyze the various components of the proposed project, it is important that we not only keep you informed, but we hear your feedback.

As the project develops, we will:

Continue outreach by communicating with legislators, homeowner associations and other identified stakeholders; and Provide ongoing communications through informational materials, mailings, email updates and a project website.