Skip to Content

Choose Your State of Service

In order to serve you better, please select your Dominion Energy location services.

Choose Your State of Service

In order to serve you better, please select your Dominion Energy location services.

Select my State

Show Dominion.com Menu

The Virginia State Corporation Commission (SCC) has regulatory authority over all energy providers in Virginia. Among other responsibilities, the SCC validates the need for a proposed line and approves the route and structures. In reviewing a proposed project, the SCC must consider whether potential impacts on scenic assets, historic districts and the environment have been reasonably minimized.

On 6/13/24, Dominion Energy filed its application with the SCC. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2024-00105 in the " Search Cases " section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments. Please note, the mailbox may not be available until a scheduling order is issued, typically several weeks after an application is filed.

To learn more about this process, view our SCC process map.

SCC Timeline

(updated 7/16/2024)

  • August 14, 2024 – Landowners Notice, Publish Notice, and Government Officials Notice
  • August 30, 2024 – Proof of Notice & Service & Certificate of Mailing to Landowners
  • September 13, 2024 – Notice of Participation deadline
  • October 4, 2024 – Respondent Testimony Due
  • October 18, 2024 – Staff Testimony Due
  • November 1, 2024 – Company Rebuttal Testimony Due
  • November 8, 2024 – Public witness sign-up and deadline for interested person(s) to file comments on Application
  • November 15, 2024, Telephonic – Public Witness Hearing
  • November 15, 2024 @ 10:00 a.m. In-Person – Evidentiary Hearing
caret
More Links