Spring 2028
Final restoration of impacted areas
Late 2027
Construction Complete
Spring 2025
Transmission line and substation construction
Early 2025
Site preparation activities: Access roads, forestry, and right of way preparation
Spring 2024
Project kickoff, engineering, and permitting
March 2024
Project announcement mailed to neighbors