Powerlines

Purpose

Dominion Energy South Carolina (DESC) will rebuild an existing electric transmission line. The line is 65 miles in length and runs from the Savannah River up to Lexington, SC. Specifically, the project traverses through Stevens Creek, Edgefield, Trenton, Johnston, Ward, Batesburg-Leesville, Gilbert, and Lexington.

We will replace the existing 115 kilovolt (kV) wooden poles with self-supporting galvanized steel structures. The new line will be designed to meet all modern electric codes and will provide a stronger electrical system across DESC service territory as well as provide additional reliability and resiliency to the areas along the route. The rebuild lines will be constructed by contractors of Dominion Energy.

Benefits

  • Maintains current right of way
  • New structures located in the same general location as existing structures
  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Minimizes impact to the community and environment
  • Replaces aging infrastructure

Timeline

Line construction started in the summer of 2020 and will be completed near the end of 2022. The project is divided into several sub-projects and will be constructed in the following years:

  • 2020: Batesburg – Gilbert & Stevens Creek – Edgefield sections
  • 2021: Batesburg – Ward, Trenton – Edgefield, and various sections through Lexington County
  • 2022: Ward – Trenton and various sections through Lexington County

Contact Us

Call us M - F, 8am - 5pm

(866) 865-1466

Construction-Related Impacts

Service Interruption

Your electric service is not expected to be impacted by this project.

Equipment Lifespan

40+ Years

The equipment has been in service for 40+ years and needs to be replaced.

Traffic

This project is not expected to impact traffic.

Noise

Noise levels will be minimal; permits are in place.

Construction Times

8am - 5pm

Most work will be completed between these hours, on weekdays.

Environment

This project will not have environmental impacts.

Neighborhood

Access to surrounding neighborhoods will not be impacted.