SCC

The Virginia State Corporation Commission (SCC) is responsible for verifying the need, determining the route and reviewing the environmental impact of certain transmission lines in Virginia.

On October 6, 2022, Dominion Energy filed its application with the SCC. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2022-00167 in the “Search Cases” section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments.

To learn more about this process, view our SCC process map.

*Due to file size, document links may take some time to open on your computer or mobile device.

SCC Timeline (Updated as of February 2023):

  • February 1, 2023 – Notices of Participation deadline
  • March 6, 2023 – Respondent Testimony deadline
  • March 22, 2023 – Staff Report deadline
  • April 4, 2023 – Deadline for Public Comments
  • April 10, 2023 – Deadline for public witnesses to indicate desire to testify
  • April 11, 2023 – Dominion Energy Virginia Rebuttal deadline
  • April 18, 2023 – Public Witness Hearing, 10:00 a.m.
  • April 19, 2023 – Evidentiary Hearing, 10:00 a.m., 2nd floor courtroom SCC
  • June 14, 2023- SCC issued final order, approving
    • Northern/Unity Solution, Route Alternative 2 (orange route)
    • Interconnect Corridor A Route 1 (red route), Interconnect Corridor B Route 1 (peach route), and Interconnect Corridor D Route 4 (purple route)