2028
Reliability projects complete
Oct. - Nov. 2025
Construction complete Wishing Star to Mars 500-230 kV Project complete.
Feb. - April 2024
Begin construction Wishing Star to Mars 500-230 kV Project
Oct. - Nov. 2023
Goose Creek Substation Expansion Project complete.
June 2023
Beaumeade to Buttermilk 230 kV Reconductor Project complete.
June 2023
Beaumeade to Paragon Park 230 kV Reconductor Project complete.
June 2023
Belmont to Beaumeade 230 kV Reconductor Project complete.
November 2022 and beyond:
Continue engagement with Loudoun County officials and community engagement group; host additional Open House events
Late Fall 2022
Submit initial project application to the State Corporation Commission (SCC)
Fall 2022
Continue community engagement and host an in-person Open House event
July 2022
Meet with LREG
April – June 2022
Announce project to Loudoun County officials and establish the Loudoun Reliability Engagement Group (LREG), a small group of Loudoun County leaders representing diverse perspectives.