Upcoming
2028
Reliability projects complete
April 2028
Construction complete of the Twin Creeks to Apollo project
December 2027
Construction complete of the Aspen to Golden project
December 2026
Construction complete of the Aviator to Takeoff project
Early 2026
Begin the construction of the Twin Creeks to Apollo project.
January 2026
Begin the construction of the Aviator to Takeoff project.
October - November 2025
Construction complete of the Wishing Star to Mars project.
August 2025
Begin the construction of the Aspen to Golden project.
January 2025
SCC issues Final Order approving the Twin Creeks to Apollo project.
December 2024
SCC issues the Final Order approving the Aspen to Golden project.
2024
February - April 2024
Begin the construction of the Wishing Star to Mars 500-230 kV Project.
March 2024
Submit the Aspen to Golden application to the State Corporation Commission (SCC).
March 2024
Submit the Twin Creeks to Apollo application to the State Corporation Commission (SCC).
2023
October 2023
Announce the Aviator to Takeoff 230 kV Electric Transmission and Substation Project
June 2023
Beaumeade to Buttermilk, Beaumeade to Paragon Park, and Belmont to Beaumeade 230 kV Reconductor Projects complete.
May 2023
Announce the Aspen to Golden 500/230 kV and Twin Creeks to Apollo 230 kV projects.
April 5, 2023
SCC issues Final Order approving Wishing Star to Mars project
2022
Late Fall 2022
Submit the Wishing Star to Mars project application to the State Corporation Commission (SCC).
April – June 2022
Announce project to Loudoun County officials and establish the Loudoun Reliability Engagement Group (LREG), a small group of Loudoun County leaders representing diverse perspectives.