December
Project completed
January 2023
Construction starting south of Bull Run Substation
December 2022
Construction continuing between Johnson DP and Bull Run
July 2022
Wire Pull: Crews are schedule to pull electric transmission conductor and shield wires across I-66.
June 2022
Wire Pull: Crews are scheduled to remove electric transmission conductor across Lee Highway (Hwy 29) in Centerville, Virginia.
April 2022
Wire Pull: Crews pulled electric transmission conductors and shield wires across Lee Highway in Centreville, VA.
January 2022
Phase 2 construction begins
August 2021
Wire Pull: Crews pulled electric transmission conductor to new structures located outside of Bull Run substation.
Mid-June 2021
Access work begins
June 8th
Access letter sent to neighbors
June 2nd
Received SCC final order
April 22nd
Evidentiary Hearing, 10:00 am VA SCC, Richmond, VA
April 15th
Public Comments deadline
March 20th
Dominion Energy Virginia Rebuttal due
February 28th
Staff Report due
January 29th
Local Public Hearing, 2:00 pm and 7:00 pm at Sully District Government Center, Chantilly, VA
November 1st
Landowner, Gov't Official and Public Notice
To Be Determined
Procedural order issued; public hearing scheduled
August
File application with Virginia SCC
July 9th and 16th
Host two public open houses
May, June 2019
Meet with local elected officials; Project website launched; dedicated email/phone open; and Solicit input from cultural advocacy groups