Winter 2022 - Spring 2023
Restoration of right of way.
December
Project In-Service Completion
August
Construction begins at Hodges Ferry Substation and works north to Churchland Substation.
July
Early 2022
Right-of-way Encroachment Coordination
April
Project Announced to Public