The project will replace 16 structures that have reached the end of their service life with new structures that meet current safety and industry standards.

Benefits

  • Maintains current right of way
  • New structures located in the same general location as existing structures
  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Minimizes impact to the community and environment
  • Replaces aging infrastructure

Virtual Open House - Recording

SCC

Frequently Asked Questions

Please Select a Datasource for Faq Component

2022

April 2022
Projected in-service date

2021

Fall 2021
Anticipated construction start date
Spring
Requested date for SCC approval
March 23rd
The SCC issued its final order, approving the project
February 5th
Deadline for written or electronic comment from public on application
January 8th
Deadline for public to request SCC hold hearing on project

2020

October 14th
Procedural order issued; public hearing scheduled
Fall
Filed application with Virginia State Corporation Commission (SCC)
September 22
Hosted two virtual community meetings (Hopewell/PGC, Chesterfield)
Summer
Met with local elected officials; Project website launched; dedicated email/phone open

Construction-Related Impacts

Service Interruption

Your electric service is not expected to be impacted by this project.
Calendar symbol

Equipment Lifespan

40 Years - The time the updated equipment will last once in service.

Traffic

This project is not expected to impact traffic.

Noise

Noise levels will be minimal; permits are in place.