Upcoming
End of Summer
Complete restoration and rehab activities
2021
May 2021 - November 2021
Rebuild Phase 3 section from Plywood to Omega
April
Crews have nearly completed phase 1 work from Kinderton-Omega. Work is beginning on phases 2 and 3.
April - June
Rebuild Phase 2 section from Buggs Island to Kinderton
March
Project update postcard sent to community
Postcard
January
Foundation installation on phase 1 from Kinderton-Omega is nearly complete. Crews continue to install structures and pull in conductor wire.
2020
April 2020 - May 2021
Rebuild Phase 1 section from Kinderton to Omega
Spring
Begin forestry activities, build access roads, and install environmental controls
2019
Fall 2019 - Spring 2020
Preliminary planning, wetland delineations, and access reviews