Choose Your State of Service

In order to serve you better, please select your Dominion Energy location services.

Choose Your State of Service

In order to serve you better, please select your Dominion Energy location services.

Select my State

Show Dominion.com Menu
2021
February 11th
The SCC issued its Final Order approving the Bristers-Ladysmith 500 kV Rebuild Project.
Document
Q1 2021
Requested date for SCC approval
2020
November 19th
Cancelled - Evidentiary hearing (10 a.m. at SCC or electronically TBD)
November 18th
Cancelled - Public witness hearing (by phone and SCC webcast)
November 17th
The SCC Hearing Examiner ruled that based on consideration of the filings and absent any public comment/testimony, that the public witness hearing scheduled for Nov.18, 2020 and the hearing scheduled for Nov. 19, 2020, are both cancelled.
Document
May 15th
File application with the Virginia State Corporation Commission (SCC)
April
Community engagement continues. Project video and simulation public launch.
February - March
Met with local elected officials; Project website launched; Dedicated email/phone open; Solicit input from cultural advocacy groups

Construction Timeline

Upcoming
December 2022
Target Completion date for Phase 1 – Bristers Chancellor
2022
Fall 2022
Phase 2 - Chancellor-Ladysmith Preconstruction activity expected to begin
2021
May
Pre-construction activity began at Bristers Substation, working south toward Chancellor Substation.
April
Letter sent to Phase 1 of the project (Bristers-Chancellor) about construction activity beginning.

Related Links

caret
More Links