Curtailment Notices

This page will be updated as soon as practical after a Curtailment Notice is called. This web page is not the primary means of curtailment notification.

Potential Curtailment Request Schedule

Summer

  • May 16 through September 30
  • Potential operation is from 2:00 p.m. to 9:00 p.m.
  • Total requests limited to 19.

Winter

  • December 1 to March 31
  • Potential operation is from 6:00 a.m. to 11:00 a.m. and from 5:00 p.m. to 10:00 p.m. (However, if both morning and evening operations are called on the same day, they will be counted as two individual requests.)
  • Total requests limited to 13.

Curtailment Notices Called for 2018/2019

2018 Summer Season

Notice date and time period

  • Curtailment Notice #1 June 18, 2018 1400 to 2100
  • Curtailment Notice #2 June 19, 2018 1400 to 2100
  • Curtailment Notice #3 June 28, 2018 1400 to 2100
  • Curtailment Notice #4 June 29, 2018 1400 to 2100
  • Curtailment Notice #5 July 2, 2018 1400 to 2100
  • Curtailment Notice #6 July 3, 2018 1400 to 2100
  • Curtailment Notice #7 July 5, 2018 1400 to 2100
  • Curtailment Notice #8 July 16, 2018 1400 to 2100
  • Curtailment Notice #9 July 27, 2018 1400 to 2100
  • Curtailment Notice #10 August 5, 2018 1400 to 2100
  • Curtailment Notice #11 August 6, 2018 1400 to 2100
  • Curtailment Notice #12 August 7, 2018 1400 to 2100
  • Curtailment Notice #13 August 8, 2018 1400 to 2100
  • Curtailment Notice #14 August 9, 2018 1400 to 2100
  • Curtailment Notice #15 August 10, 2018 1400 to 2100
  • Curtailment Notice #16 August 16, 2018 1400 to 2100
  • Curtailment Notice #17 August 17, 2018 1400 to 2100
  • Curtailment Notice #18 August 27, 2018 1400 to 2100
  • Curtailment Notice #19 August 28, 2018 1400 to 2100



Past Notices