Buggs Island-Plywood

Buggs-Plywood

After more than five decades of operation, the wooden pole and H-frame structures and associated components along the nearly 26-mile line running from our Buggs Island Substation in Mecklenberg County to our Plywood Substation in Halifax County need to be replaced in order to maintain reliability for our customers.

Project Goals

Our suggested approach is to rebuild this line in a manner that:

  • Upgrades the line the current 115 kV standards.
  • Maximizes use of the existing right of way corridor.
  • Maintains reliable service to over 2,000 Mecklenberg Electric Cooperative customers served by a substation connected to the line.

Project Updates 

  • March 2020 Meeting Cancelled. New date and time TBD. View the cancellation postcard.
  • February 2020 - Landowners sent invitation to construction informational meeting.
  • November 2019 - Soil borings completed at different structure locations along the line.
  • October 2019 - Postcard sent to landowners announcing projects.

Construction and access plans listed below, 

Virtual Open House

For more information about construction, please visit our Virtual Open House.


Maps:

Existing project map


Anticipated Project Schedule:

Fall 2019 - Spring 2020 - Preliminary planning, wetland delineations, and access reviews. 

Spring 2020Begin forestry activities, build access roads, and install environmental controls.

April 2021 - May 2021 Rebuild Phase 1 section from Kinderton to Omega

April 2021 – June 2021Rebuild Phase 2 section from Buggs Island to Kinderton

May 2021 – November 2021 - Rebuild Phase 3 section from Plywood to Omega

End of summer 2022 – Complete restoration and rehab activities