The Morrisville–Wishing Star 500 & 230 Kilovolt (kV) Project is a vital infrastructure upgrade spanning Fauquier, Prince William, and Loudoun counties. The project includes:

  • Installing a new 500 kV transmission line along or near 36.5 miles of existing right of way (ROW)
  • Adding a new 230 kV transmission line in Fauquier County
  • Expanding the Morrisville Substation

These improvements will strengthen our electric grid, improve efficiency, and ensure continued reliability.

Dominion Energy has proposed a primary route and evaluated several alternatives along the full route. We invite your input.

Updates

  • May 2026: The Virginia State Corporation Commission issued the Order for Notice and Hearing setting forth the procedural schedule in Case No. PUR-2026-00021.Please view the Legal tab.
  • February 2026: Dominion Energy filed its application with the SCC. Please view the Legal tab for the complete application.
  • December 2025: During ongoing engineering design, our engineering team identified construction and outage challenges within the Pageland 1 alternative route that were caused by the multiple east-to-west crossings of existing corridor. Therefore, the Pageland 1 alternative route was updated to eliminate these challenges by replacing two eastern expansion areas in the previous route with an 85-foot-wide western expansion of the existing corridor south of Sudley Road in Prince William County.
  • October 2025 Update: After further analysis, our engineering team has eliminated the alternative routes in Segment 2B (Fauquier) and a portion of Segment 3 (Prince William). These alternatives will be described in Dominion’s CPCN application as “considered but eliminated” and will not be offered to the SCC as a viable routing option.
  • August 2025 Update: After continued evaluation, public feedback, and input, the alternative routes previously identified in Segment 1 in Fauquier County have been eliminated for consideration.
  • July 2025 Update: At this time, Dominion Energy has not yet submitted an application to the Virginia SCC. We are continuing our routing analysis for the Morrisville–Wishing Star project and taking into account feedback we’ve heard from our community meetings. We expect to file an SCC application by late 2025 or early 2026.
  • June 2025 Update: After continued evaluation, public feedback, and input, the three alternative routes previously identified in Loudoun County have been eliminated for consideration. View the updated announcement.

Timeline

  • March–November 2025 – Public outreach and engagement
  • Early 2026 – Submit application to the State Corporation Commission (SCC)
  • 9–12 months after filing – Anticipated SCC approval
  • Spring 2027 – Begin project construction
  • Summer 2030 – Construction completed

Benefits

  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Minimizes impact to the community and environment
  • Strengthens area reliability

FAQ

Construction Methods & Right-of-Way

Both boring and trenching require a similar right-of-way width due to equipment access, safety buffers, and space needed for staging and spoil management.
While wreck and rebuild can be used in specific segments, constraints such as reliability requirements and existing infrastructure prevent its use along the entire corridor.
Dominion Energy is evaluating construction methods segment by segment and will consider wrecking and rebuilding where technically feasible.

Environmental & Visual Mitigation

Yes, undergrounding was considered; however, it presents significant technical, environmental, and cost challenges, particularly in historically sensitive areas like the Manassas National Battlefield Park.

Need & Justification

The demand for reliable electricity has grown significantly since 2008, driven by regional load growth, including data center development. The new line addresses current and projected capacity and reliability needs.

Alternatives Analysis

Alternate “greenfield” routes are being considered in areas where wrecking and rebuilding or expanding the right-of-way would not be feasible due to existing development. 
Yes, developing new greenfield routes often requires more land acquisition, permitting, and environmental review, making them generally more expensive and complex than expanding within an existing corridor.

Regulatory, Legal & Access Issues

 Yes, conservation easements often include restrictions that limit development. Dominion Energy must evaluate these on a case-by-case basis and may require legal agreements or approvals to proceed.
 

Maps

Three maps included with the Project SCC Application are shown below, including a one-page overview map and two zoomed-in map series showing constraints and the areas of existing and new Project right-of-way.

 

  1. Attachment II.A.1 Proposed and Alternative Routes
  2. Attachment II.A.2 Constraints
  3. Attachment II.A.6 Right-of-Way Subject to New and Existing Easements
  4. Typical Structures

Legal

The Virginia State Corporation Commission issued the Order for Notice and Hearing setting forth the procedural schedule in Case No. PUR-2026-00021.

Key dates are as follows:

  • On or before May 22, 2026 - Government Officials Notice (to include attorneys)
  • On or before May 22, 2026 – Landowners Notice Deadline
  • On or before May 22, 2026– Newspaper Publication Deadline (as shown in Attachment II.A.1 on pages 580-581 of the Appendix to the Application)
  • On or before May 29, 2026– Proof of Notice & Service and Certificate of Mailing Due
  • On or before June 17, 2026– Notice of Participation Deadline
  • On or before August 13, 2026– Respondent Testimony Due
  • On or before September 15, 2026– Staff Testimony Due
  • On or before September 29, 2026– Company Rebuttal Testimony Due
  • On or before September 25, 2026– Deadline for Public Witness Sign-up
  • Wednesday, September 30, 2026– Public Witness Hearing (Telephonically at 10:00 A.M.)
  • On or before October 30, 2026– Deadline for Public Comments on the Application
  • Monday, November 16, 2026– Public Evidentiary Hearing starting at 10:00 A.M., and continuing November 17-20, 23, and 24, 2026 as needed.

The Virginia State Corporation Commission (SCC) is responsible for verifying the need, approving the route and structures and reviewing the environmental impact of certain transmission lines in Virginia. On February 27, 2026, Dominion Energy filed its application with the SCC.

Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2026-00021 in the "Search Cases" section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments.

Upcoming Meetings

Wednesday, November 19, 2025
In-person Open House (Prince William County)
George Mason University's SciTech Campus
Beacon Hall

June 2, 2025
Virtual Open House
View the Presentation - June 2, 2025

May 21, 2025
In-person Open House (Loudoun County)
The Lodge at Hanson Park
Aldie, VA

May 15, 2025
In-person Open House (Prince William County)
Patriot High School
Nokesville, VA

May 13, 2025
In-person Open House (Fauquier County)
Mary Walter Elementary
Bealeton, VA

May 5, 2025
Virtual Open House
View the Presentation - May 5, 2025
View Recording - May 5, 2025

Community Engagement

Public Engagement Process

Public participation and involvement are vital to project planning and execution. At Dominion Energy we strive to improve the physical, social, and economic well-being of the communities we serve.

Once a project need is identified, conceptual project planning and design begins. Dominion Energy consults with key stakeholders throughout the planning process to gather and incorporate feedback into design plans. Key stakeholders include local, county, and state officials, state and federal agencies, historic preservation and natural resource groups, Native American tribes, and community members.

Dominion Energy encourages all stakeholders to learn more about Fauquier County, Prince William County and Loudoun County Electric Transmission Projects and submit feedback. You can contact the project team by email at powerline@dominionenergy.com or +1 888-291-0190.

Documents

What Matters To You?

Explore GeoVoice, an interactive mapping tool. You can:

  • Search for your address
  • Send feedback to the project team

We want to hear from you. Sign-up Today.

Explore GeoVoice cta btn

Powerlines 101 - Learning Zone

Learn how the energy grid works, along with our processes to build and maintain electric transmission lines.

Discover more about your lines cta btn