Urquhart-Toolebeck
Overview

Benefits
- Complies with mandatory standards to ensure safety, reliability and to meet future needs
- Minimizes impact on the community and environment
- Improves future reliability for Lowcountry
Timeline
Engineering design and environmental permitting began early 2025. Right of way acquisition will begin in spring 2025. Transmission line construction will begin in spring 2026. In addition to weekdays and normal work hours, weekend work hours may be necessary to meet critical project schedules.Call us M - F, 8am - 5pm
(866) 865-1466Email us at
SCPowerLine@dominionenergy.comConstruction-Related Impact

Service Interruption
Your electric service is not expected to be impacted by this project.

Neighborhood
Access to surrounding neighborhoods will not be impacted.

Traffic
This project is not expected to impact traffic.

Environment
This project will not have environmental impacts.

Noise
Noise levels will be minimal; permits are in place.