Thrasher - Fentress 230 kV Electric Transmission Line

This work is necessary to accommodate future load growth, uphold federal electric reliability standards, and strengthen the grid.

Benefits

  • Complies with mandatory standards to ensure safety, reliability and to meet future needs 
  • Minimizes impact to the community and environment 
  • Strengthens area reliability 
  • Strengthens operational flexibility 

Timeline

January 2026

  • Project Announcement

June 2026

  • Finalize:
  • - Permitting
    - Engineering
    - Pre-Construction Outreach

July 2026

  • Open House
  • Community Outreach Continues

October 2026 

  • Construction to Begin

Early 2027

  • Construction Complete; Restoration Begins

Construction-Related Impacts

  • Your electrical service is not expected to be impacted by this project
  • This project is not expected to impact traffic
  • Noise levels will be minimal; permits are in place
  • This project will not have environmental impact
  • Access to surrounding neighborhoods may be impacted