How can we help you?
Technology Blvd. Electric Transmission Project
Support growing energy demands in Eastern Henrico County.
Overview

To support growing energy demands in eastern Henrico County, Dominion Energy is proposing new electric transmission infrastructure to meet the growing energy needs, continue reliable electric service, and maintain compliance with federal reliability standards.
Benefits
- Complies with mandatory standards to ensure safety, reliability and to meet future needs
- Strengthens area reliability
- Strengthens operational flexibility
Documents
Impacts
Legal
The Virginia State Corporation Commission (SCC) is responsible for verifying the need, determining the route, and reviewing the environmental impact of certain transmission lines in Virginia. Dominion Energy plans to file an application with the SCC for this project. After filing, documents related to the case will be available to the public on the SCC website. Key filing documents will also be available on this page.
On 3/7/25, Dominion Energy filed its application with the SCC. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2025-00042 in the " Search Cases " section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments. Please note, the mailbox may not be available until a scheduling order is issued, typically several weeks after an application is filed.
To learn more about this process, view our SCC process map.
- May 2, 2025– Landowner Notice, Publication Deadline, and Government Official Notice (to include Attorneys)
- May 23, 2025– Proof of Notice and Certificate of Mailing deadline
- June 9, 2025– Notice of Participation deadline
- July 9, 2025– Respondent Testimony due
- August 4, 2025– Staff Report due
- August 18, 2025– Company Rebuttal Testimony due
- September 9, 2025- Public witness signup deadline
- September 9, 2025- Any interested person may submit comments on the Application (on or before)
- September 16, 2025- Telephonic Hearing for Public Witness Testimony (10:00 A.M)
- September 16, 2025– at 10:00 A.M. (In-Person) Public Evidentiary Hearing
Meetings
Thursday, January 23, 2025
6-8 p.m.
Community Meeting
Lumber Liquidators Building
6115 Technology Creek Drive
Sandston, VA 23150
View boards on display at the community meeting:
Timeline
Upcoming
2027
Construction
Q1 2026
Anticipated SCC ruling
2025
Q1 2025
File application with the Virginia State Corporation Commission (SCC)
2025-2026
Permitting Finalize engineering Pre-construction outreach
2024
Fall 2024
Project announcement - Public Outreach
FAQs
To support recent growth within the White Oak Technology Park, a new double-circuit 230 kilovolt (kV) electric transmission source is needed to meet the new power needs, maintain federal reliability rules, and keep the grid operating efficiently.
Our project team will focus on public outreach in fall 2024 to ensure all interested community members are aware of the project and have an opportunity to share feedback with our team as we continue the planning process. We intend to file an application with the SCC in early 2025.
The SCC is the regulatory body with jurisdiction over transmission lines in Virginia. Since this project is proposing to build a new 230 kV infrastructure, it meets the criteria to be reviewed by the SCC. Dominion Energy intends to file an application in 2025.
Although the SCC is the primary agency reviewing and ultimately approving the project, there may be additional permits needed from local, state, and federal agencies.
We want to hear your feedback. The purpose of our public engagement is to share, listen and learn from our community members. The SCC also considers public input in its review process. There are multiple ways to share your feedback with our team:
- Contact us by email at powerline@dominionenergy.com or by phone at 888-291-0190.
- Attend our community meeting
- Invite us to your community or property
Interested community members are welcome to request a separate meeting with our team. Whether you have a scheduling conflict during the community meeting date, would like to discuss your property specifically, or would like to continue a discussion with our team following the community meeting, we are available for additional meetings by request.

Service Interruption
Your electric service is not expected to be impacted by this project.