Staunton-Valley

Find a project through the regions or by using the map.

Overview

Lineworker in front of Dominion Energy truck

Most of the existing structures and components along this 21.5-mile line corridor have been in service for nearly five decades. To maintain reliability for our customers and due to the age of some components, the line is being replaced. The line was primarily built on wooden H-frame structures. In some locations, it also used brown, weathering steel lattice structures and monopole structures.

We are replacing the double circuit weathering-steel lattice structures primarily with brown, weathering-steel monopoles. The single circuit wooden H-frame structures are being replaced with brown, weathering steel H-frame structures with galvanized cross arms and x-braces.

Benefits

  • Upgrades the line to current 230 kV standards
  • Utilizes the existing right of way

Timeline

  • August 2022 – SCC issued Final Order approving project
  • Summer 2023 –Phase I (Valley Substation-West Staunton Substation) construction began
  • Early 2024 – Phase II (West Staunton Substation-Staunton Substation) construction began
  • Summer 2024 - Phase I construction complete (expected)
  • Late 2025 – Project complete (expected)
     

Purpose

The key purpose of this project is to replace aging infrastructure and rebuild to current reliability standards.

Existing Transmission Corridor Conditions:

  • Project area is 21.5 miles long
  • Right of way is primarily 120 feet wide with some 100-foot sections
  • Double circuit monopoles and lattice structures
  • Single circuit wood H-frames
  • Previous average structure height: 73.3'
  • Previous average single-circuit structure height: 64.7'
  • Previous average double-circuit structure height: 122.4'

Proposed Transmission Corridor Conditions

  • Utilize existing right of way corridor
  • Brown, weathering-steel H-frames with galvanized cross arms and x-braces
  • Brown, weathering-steel monopoles, and 3-pole structures in some areas
  • New average structure height: 80.1'
  • New average single-circuit structure height: 72'
  • New average double-circuit structure height: 126.7'

SCC Approval Process

On November 12, 2021, Dominion Energy filed its application for this project with the SCC. The SCC issued its Final Order approving the project on August 31, 2022.

The Virginia State Corporation Commission (SCC) has regulatory authority over all energy providers in Virginia and requires certification for all transmission lines out of the ordinary course of doing business. Among other responsibilities, the SCC validates the need for a proposed line and approves the route and structures. In reviewing a proposed project, the SCC must consider whether potential impacts on scenic assets, historic districts and the environment have been reasonably minimized.

To learn more, please view our SCC application review process .

Pre-Construction Open House

On May 3, 2023, our project team hosted an in-person open house for community members to learn more about this project, ask questions, and interact with our project team.

Missed the meeting? Contact us with your questions by sending an email to powerline@dominionenergy.com or by calling 888-291-0190.

Virtual Community Meeting

Miss the Sept. 14, 2021 virtual community meeting?

View the virtual community meeting recording!

Timeline

Upcoming

Late 2025
Project complete (expected)

2024

Summer 2024
Phase I (Valley Substation-West Staunton Substation) construction complete (expected)
Early 2024
Phase II (West Staunton Substation-Staunton Substation) construction began

2023

Summer 2023
Phase I (Valley Substation-West Staunton Substation) construction began
May 2023
Hosted in-person pre-construction community open house

2022

Fall 2022–Spring 2023
Completed pre-construction activities
August
SCC issued Final Order approving project

2021

November
Submitted SCC application
Q2 2021–Q2 2023
Permitting activities, coordination with stakeholders, and conceptual design
April
Project announcement sent to community

Construction-Related Impacts

Traffic

There may be some traffic delays.

Environment

This project will not have environmental impacts.

Neighborhood

Access to surrounding neighborhoods may be impacted.