Skiffes Creek – Yorktown

Dominion Energy is proposing to rebuild the existing segment of 230kV transmission line between the Skiffes Creek substation and C&O Junction.

Project Details

After five decades of reliable service, the infrastructure along this segment of electric transmission line is nearing its end of service life and needs to be replaced to maintain reliability. This project will not require new Right of Way (ROW.)

Documents

Community Meetings

You are invited to attend an upcoming community meeting where Dominion Energy’s subject matter experts will share information and answer questions about this project:

  • Wednesday, June 10, 2026
    5-7 p.m.
    Beechwood Recreation Association
    903 Colleen Drive
    Newport News, VA 23608

Timeline

2026

Spring 2026
Project Announcement
Summer 2026
Community Meeting
Mid-Summer 2026
Filing with the Virginia State Corporation Commission (SCC)

2027

Spring 2027
Anticipated SCC Ruling Fall

2028

Fall 2028
Construction to begin

2029

Late 2029
Construction Complete

Legal

The Virginia State Corporation Commission (SCC) has regulatory authority over all energy providers in Virginia. Among other responsibilities, the SCC validates the need for a proposed line and approves the route and structures. In reviewing a proposed project, the SCC must consider whether potential impacts on scenic assets, historic districts and the environment have been reasonably minimized.

Our SCC application review process

Once this project is submitted to the SCC, we will post our application and provide a link to the SCC’s case docket where you will find documents related to the case, as well as information on how to submit comments.

Powerlines 101 - Learning Zone

Learn how the energy grid works, along with our processes to build and maintain electric transmission lines.
Discover more about your lines cta btn