Septa-Yadkin

Project Overview

Powerlines Landscape
We are proposing to rebuild an aging 500 kilovolt (kV) electric transmission line between our Septa and Yadkin substations. The structures and related components along this 33.1-mile corridor running through Isle of Wight, Suffolk and Chesapeake, Virginia, have reached the end of their life service and need to be replaced to maintain reliability. This project requires no new right of way.

Community Meeting

You are invited to our community meeting to learn more about the Septa-Yadkin 500kV Electric Transmission Project. Our project team members will be in attendance to discuss routing options, answer your questions and review project plans.

Wednesday, April 9, 2025
5-7 p.m.


Hilton Garden Inn: Suffolk Riverfront
100 E Constance Road
Suffolk, VA 23434

GeoVoice: Structure Comparison Tool

Septa-Yadkin Interactive Structure Comparison Tool, GeoVoice

  • Use the address search to see structure locations in your area.
  • View details about individual structures by clicking on structure location marker.
  • View simulations of existing and proposed structures.
Interactive Structure Comparison Tool cta btn

Benefits

  • Maintains current right of way.
  • Complies with mandatory standards to ensure safety, reliability and to meet future needs.
  • Minimizes impact to the community and environment.
  • Replaces aging infrastructure.
  • Strengthens area reliability.
  • Strengthens operational flexibility.

Timeline

  • December 2024 – Project Announcement
  • April 2025 – Community Meeting
  • Spring 2025 – SCC Filing
  • Early 2026 – Anticipated SCC Ruling
  • Mid-2026 – Construction to begin
  • 2029 – Construction complete 

Documents

Legal

The Virginia State Corporation Commission (SCC) is responsible for verifying the need, determining the route, and reviewing the environmental impact of certain transmission lines in Virginia. Key filing documents will also be available on this page. 

On June 5, 2025, Dominion Energy filed its application with the SCC. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2025-00104 in the Search Cases section. In addition, interested parties may visit the SCC Case Comments page where individual mailboxes are available for each case accepting public comments. Please note, the mailbox may not be available until a scheduling order is issued, typically several weeks after an application is filed. 

To learn more about this process, view our SCC process map.

Impacts

Traffic

This project is not expected to impact traffic.

Noise

Noise levels will be minimal; permits are in place.

Environment

This project will not have environmental impacts.

Neighborhood

Access to surrounding neighborhoods will not be impacted.