Remington - Gainesville

Area Reconductor Projects

Overview

Dominion Energy employee in a hard hat stands, hands on hips, beside a truck

To help maintain electric transmission reliability and comply with mandatory federal standards, Dominion Energy is making improvements to electric transmission infrastructure in Fauquier and Prince William counties in Virginia.

These upgrades will replace the wires, a process called reconductoring, on several electric transmission lines running north from Remington to Gainesville, and east to Manassas. To maintain a safe distance around the new wires, some of the transmission structures need to be raised by up to 25 feet. This will be accomplished with an innovative process which will allow us to safely raise the structures without interrupting electric service. Learn more about the process.

Electric Transmission

Benefits

  • Maintains current right of way
  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Minimizes impact to the community and environment
  • Strengthens area reliability

Construction-Related Impact

Low impact symbol

Service Interruption

Your electric service is not expected to be impacted by this project.
Medium impact symbol

Traffic

There may be some traffic delays.
Low impact symbol

Noise

Noise levels will be minimal; permits are in place.
Low impact symbol

Environment

This project will not have environmental impacts.
Low impact symbol

Neighborhood

Access to surrounding neighborhoods will not be impacted.

Timeline

Fall 2026
Vint Hill - Liberty reconductor complete
January 2026
Vint Hill - Liberty structure lifts complete; reconductor begins
Late 2025
Remington - Rollins Ford Phase 3 and 4 reconductor complete
October 2025
Vint Hill - Liberty structure lifts begin
Spring 2025
Remington - Rollins Ford Phase 3 and 4 reconductor begins
Fall 2024
Remington - Rollins Ford Phase 3 and 4 structure lifts begin
Spring 2024
Remington - Rollins Ford Phase 2 reconductor complete
Early 2024
Remington - Rollins Ford Phase 2 structure lifts complete
Early 2024
Remington - Rollins Ford Phase 2 structure lifts begin
Early 2024
Remington - Rollins Ford Phase 2 reconductor access and construction begin
Late 2023
Remington - Rollins Ford Phase 1 reconductor complete
Fall 2023
Remington Substation reconductor begins
Summer 2023
Remington - Rollins Ford Phase 1 access installation begins
2022
Remington - Rollins Ford work begins

Powerlines 101 - Learning Zone

Learn how the energy grid works, along with our processes to build and maintain electric transmission lines.
Discover more about your lines cta btn