Park Center

230 kV Electric Transmission Line and Substation Project

Lineworker in front of Dominion Energy truck
As data centers continue to develop, new electric infrastructure is needed to help strengthen the bulk electricity grid and maintain reliable service for our customers. This project includes a new substation, known as Park Center Substation, in Fairfax County. New 230 kilovolt (kV) electric transmission lines will be needed to connect the Park Center Substation to an existing transmission line just west of the substation. New right of way is needed for this project. We are currently reviewing three routing options for this double-circuit transmission line, all of which are just about or less than a quarter of a mile.

Double-Circuit Monopole Structures

*Examples of electric transmission double-circuit monopole structures. Not project specific.

Double-Circuit Monopole Structures
Double-Circuit Monopole Structures
Double-Circuit Monopole Structures
Double-Circuit Monopole Structures

Benefits

  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Minimizes impact to the community and environment

Timeline

  • July - September 2022
    Initial Public Outreach
  • August 2022
    Virtual Community Meeting
  • TBD 2023
    Submit Virginia State Corporation Commission Application
  • Q2 2024
    Estimated Construction Start
  • Q2 2025
    Target Project Completion

Documents

Construction Related Impacts

The Virginia State Corporation Commission (SCC) is responsible for verifying the need, determining the route and reviewing the environmental impact of certain transmission lines in Virginia.

The company intends to file an application with the SCC. Documents related to the case will be available to the public on the SCC Docket of the SCC website once the application is received a docket recreate. Interested parties may comment directly to the SCC regarding this project by sending an email to sccinfo@scc.virginia.gov.

To learn more about this process, view our SCC process map.

Virtual Community Meeting

August 2, 2022

2025

Q2 2025
Target Project Completion

2024

Q2 2024
Estimated Construction Start

2023

TBD 2023
Submit Virginia State Corporation Commission Application

2022

August 2022
Virtual Community Meeting
July - September 2022
Initial Public Outreach

Service Interruption

Your electric service is not expected to be impacted by this project.

Traffic

This project is not expected to impact traffic.

Environment

This project may have limited environmental impacts.

Neighborhood

Access to surrounding neighborhoods will not be impacted.