Mt. Storm - Valley
Overview

This project will rebuild an existing 500 kilovolt line running southeast from West Virginia’s Grant, Hardy and Pendleton counties into Virginia’s Rockingham and Augusta counties. The line has been in operation for over five decades and needs to be replaced to maintain reliability for our customers. A total of 261 structures will be replaced on the 64-mile line – including 258 brown, weathering steel lattice structures. The new proposed galvanized steel lattice structures will stand 118 feet tall on average, or about 15 feet taller on average than the existing structures.
Benefits
- Creates no new right of way
- Keep structures in the same general location as existing structures
- Provide long-term reliability and durability without excessive maintenance
- Comply with mandatory standards to ensure safety and reliability
The interactive mapping tool provides up-to-date information related to road closures and delays in and around the George Washington National Forest from construction activities.
Maps and Simulations
Maps
Photo simulations
SCC Application
The Virginia State Corporation Commission (SCC) has regulatory authority over all energy providers in Virginia. Among other responsibilities, the SCC validates the need for a proposed line and approves the route and structures. In reviewing a proposed project, the SCC must consider whether potential impacts on scenic assets, historic districts and the environment have been reasonably minimized.
Application Documents
Interactive Mapping Tool
The interactive mapping tool will provide up-to-date information related to road closures and delays in and around the George Washington National Forest from construction activities.
Past Events
Virtual Community Meeting - WebEx Event
Did you miss our Mt. Storm-Valley Phase 2 virtual community meeting?
Timeline
2023
Third Quarter 2023
Target construction completion of the final phase, phase 3
2022
January
Preconstruction Virtual Meeting for Phase 3
2021
Second Quarter
Construction Completed on Phases 1, 2, & 2A
2019
May 30
Construction informational meeting for West Virginia landowners held at Petersburg (WV) High School
Spring
File SCC Application
2018
August 14
Hosting community open house at Ottobine Elementary School
View August 14 & 16 meeting postcard
April
Project Announced
August 16
Hosting community open house at North River Elementary School
View August 14 & 16 meeting postcard