Mt. Storm - Valley

Overview

Powerlines Female Lineworker
This project will rebuild an existing 500 kilovolt line running southeast from West Virginia’s Grant, Hardy and Pendleton counties into Virginia’s Rockingham and Augusta counties. The line has been in operation for over five decades and needs to be replaced to maintain reliability for our customers. A total of 261 structures will be replaced on the 64-mile line – including 258 brown, weathering steel lattice structures. The new proposed galvanized steel lattice structures will stand 118 feet tall on average, or about 15 feet taller on average than the existing structures.

Benefits

  • Creates no new right of way
  • Keep structures in the same general location as existing structures
  • Provide long-term reliability and durability without excessive maintenance
  • Comply with mandatory standards to ensure safety and reliability

The interactive mapping tool provides up-to-date information related to road closures and delays in and around the George Washington National Forest from construction activities.

SCC Application

The Virginia State Corporation Commission (SCC) has regulatory authority over all energy providers in Virginia. Among other responsibilities, the SCC validates the need for a proposed line and approves the route and structures. In reviewing a proposed project, the SCC must consider whether potential impacts on scenic assets, historic districts and the environment have been reasonably minimized.

Application Documents

Interactive Mapping Tool

The interactive mapping tool will provide up-to-date information related to road closures and delays in and around the George Washington National Forest from construction activities.

Past Events

Virtual Community Meeting - WebEx Event

Did you miss our Mt. Storm-Valley Phase 2 virtual community meeting?

Watch the Video

Timeline

2023

Third Quarter 2023
Target construction completion of the final phase, phase 3

2022

January
Preconstruction Virtual Meeting for Phase 3

2021

Second Quarter
Construction Completed on Phases 1, 2, & 2A

2019

May 30
Construction informational meeting for West Virginia landowners held at Petersburg (WV) High School
Spring
File SCC Application

2018

November
Project update postcard sent to neighbors
View SCC filing change postcard
September
Postcard sent to neighbors announcing soil boring activities
View surveying postcard
August 14
Hosting community open house at Ottobine Elementary School
View August 14 & 16 meeting postcard
April
Project Announced
August 16
Hosting community open house at North River Elementary School
View August 14 & 16 meeting postcard