How can we help you?
Glebe
Electric Transmission Project
Overview

The Glebe Electric Transmission Project will allow Dominion Energy to continue providing reliable electric service to the area. The project involves 3 main components:
- Rebuilding and modernizing the Glebe Substation in Arlington County, which was built in the 1970s and is reaching its end of service life.
- Converting an existing overhead electric transmission line to an underground line between the Glebe Substation and Potomac Yard Transition Station.
- Decommissioning of the Potomac Yard Transition Station in the City of Alexandria and the existing overhead line from service.
Documents
Maps
For more visuals and information about the project, including a video, visit our interactive web page.

Legal
SCC Application
The Virginia State Corporation Commission (SCC) has regulatory authority over all energy providers in Virginia. Among other responsibilities, the SCC validates the need for a proposed line and approves the route and structures. In reviewing a proposed project, the SCC must consider whether potential impacts on scenic assets, historic districts and the environment have been reasonably minimized.
On March 7, 2019, Dominion Energy filed its application with the SCC. The SCC issued its Final Order approving the project on September 27, 2019. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2019-00040 in the "Search Cases" section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments.
SCC Timeline
- April 14, 2022 – Order Granting Motion for Extension of Construction and In-Service Date
- March 7, 2022 – Company filed motion for Extension of Construction and In-service date
- Sept. 27, 2019 – SCC final order issued approving the Glebe Rebuild project.
- Aug. 13, 2019 – SCC Hearing Examiner's Report issued in response to the proposed project.
- July 23, 2019 – A public evidentiary hearing will be held at 10:00 am in the SCC’s second floor courtroom located at 1300 East Main St., Richmond, VA 23219
- By July 16, 2019 – Any interested person may file written or electronic comments on the application (referencing Case No. PUR-2019-00040).
- On or before July 9, 2019 – Dominion Energy may file any rebuttal
- On or before June 25, 2019 – The SCC staff must file a report and exhibits on its investigation of Dominion Energy’s application.
- By April 23, 2019 – Dominion Energy must publish a legal notice of the application
- March 25, 2019 – The SCC issued an Order of Notice and Hearing.
- March 7, 2019 – Dominion Energy filed an application for a Certificate of Public Convenience and Necessity with the Virginia State Corporation Commission (SCC) to rebuild its Glebe Substation and underground North Potomac Yards.
Meetings
Wednesday, May 11, 2022
Virtual Community Meeting
6:30 p.m.
Live via WebEx Events
Miss the meeting? View the recording.
Timeline
2025
Late 2025
Existing overhead transmission line and transition station removal (second detour of Four Mile Run Trail); target completion date; restoration of work area
2024
Mid–late 2024
Replace existing chain-link fence with new metal mesh security fence
April 2024
All tunneling construction activities complete; begin to backfill launch and receiving pits, and to construct transmission line access manholes
2023
December 2023
Micro tunneling complete for second tunnel; begin to install bundle of conduits within both tunnels
September 2023
Micro tunneling begins for second tunnel between launch and receiving pits
August 2023
Receiving pit complete
August 2023
Micro tunneling complete for first tunnel
July 2023
Micro tunneling begins for first tunnel between launch and receiving pits
June 3–4, 2023
Install additional non-slip coating on the temporary boardwalk diversion
May 7, 2023
Temporary boardwalk diversion opens to public
May 2023
Begin installing receiving pit at Glebe Substation. The receiving pit is needed to install the new underground line using the micro tunnel method. Truck traffic will increase on S. Eads Street.
2023–2024
Substation construction
February 2023
Completion of boardwalk for the Four-Mile Run diversion around the Glebe Substation
January 2023
Launch pit complete
2022
December 2022
Installation of sound wall around the launch pit. The sound wall is 24 feet tall and designed to reduce construction noise from the launch pit.
August 2022
Begin installing launch pit in Potomac Yard Shopping Center. The launch pit is needed to install the new underground line using the micro tunnel method.
Summer 2022
Select contractors
June–September 2022
Four Mile Run Trail closed around Glebe Substation while we install temporary boardwalk diversion
Late May 2022
Arlington County and VDOT approve Four Mile Run detour plans
May 11, 2022
Pre-construction virtual community meeting
2019
September 27, 2019
SCC issues its final order approving the Glebe Rebuild Project
August 13, 2019
SCC issues Hearing Examiner’s Report in response to the project
July 16, 2019
Any interested person may file written or electronic comments on the application (referencing Case No. PUR-2019-00040)
July 9, 2019
Dominion Energy may file any rebuttal
March 25, 2019
SCC issues Order of Notice and Hearing
March 7, 2019
Submit application to Virginia State Corporation Commission (SCC)
February 2019
Ongoing meetings with community and civic associations
Late January 2019
Submit 2,202 letters to localities; provide update to locality staff; send cultural advocacy letters to stakeholders
2010
June 25, 2010
The SCC staff must file a report and exhibits on its investigation of Dominion Energy’s application
Construction-Related Impact

Service Interruption
Your electric service is not expected to be impacted by this project.

Traffic
There may be some traffic delays.

Neighborhood
Access to surrounding neighborhoods will be impacted.
