Cemetery Road

230 kV Transmission Line and Substation

Project Overview

We are building a new Cemetery Road 115 kilovolt (kV) Substation southeast of Chase City in Mecklenburg County, Virginia. This project will improve electric reliability for all area customers. Cemetery Road Substation will serve a new natural gas compressor station, which was approved by the Federal Energy Regulatory Commission (FERC).

We are also building an approximately 0.1-mile 115 kV transmission line from a nearby line to connect the new substation to the electric grid.

Benefits

  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Minimizes impact to the community and environment
  • Strengthens area reliability

Timeline

  • Fall 2022: Site surveying
  • Early 2023: Soil boring 
  • Early 2024: Begin substation and transmission line tap construction activities
  • Fall 2024: Expected completion of substation and transmission line tap
     

Documents

Construction Related Impacts

Traffic

This project is not expected to impact traffic.

Noise

Noise levels will be moderate; permits are in place.

Neighborhood

Access to surrounding neighborhoods will not be impacted.

FAQs

Please visit https://www.williams.com/expansion-project/commonwealth-energy-connector/ to learn about the Commonwealth Energy Connector.
Please email us at powerline@dominionenergy.com or call 1-888-291-0190.

Timeline

2024

Fall 2024
Expected completion of substation and transmission line tap
Early 2024
Begin substation and transmission line tap construction activities

2023

Early 2023
Soil Boring

2022

Fall 2022
Site Surveying