Carson-Locks

230 kV Electric Transmission Rebuild Project

Project Overview

At Dominion Energy, we are dedicated to maintaining reliable and secure electric service in the communities we serve. The Carson-Locks 230 kilovolt (kV) Electric Transmission Rebuild Project proposes to rebuild and reconductor 10.34 miles of existing 230 kV transmission lines that run from the Carson Substation on Ellington Road in Dinwiddie County to the Locks Substation on Rawlings Lane in the City of Petersburg.

To maintain reliable service for our customers, we will rebuild the existing transmission line from the Carson Substation to the Locks Substation. In addition to replacing the current 230 kV wires, a process known as reconductoring, we will also replace the transmission structures. Reconductoring will increase the ampacity, or maximum current carried, on the line. The line will be rebuilt within the existing right of way; therefore, no new permanent right of way is required. The lines were built primarily with wooden H-frame structures. We are rebuilding these with mostly weathering steel (brown) H-frame structures and some monopole structures, which require less maintenance and have a longer service life. The new structures will be, on average, approximately five feet taller than the existing structures. This project will ensure the continued safety and reliability of the electric grid.

Benefits

  • New structures located in the same general location as existing structures
  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Minimizes impact to the community and environment
     

Timeline

  • Spring 2023 – Project announcement
  • Early Summer 2023 –Community meetings
  • Summer 2023 – Filed application with the Virginia State Corporation Commission (SCC)
  • Summer 2024 – SCC issued Final Order approving project
  • Summer 2024 – Anticipated construction start
  • Summer 2025 – Anticipated construction completion

Documents

Construction Related Impacts

Service Interruption

Your electric service is not expected to be impacted by this project.

Neighborhood

Access to surrounding neighborhoods will not be impacted.

Traffic

This project is not expected to impact traffic.

Noise

Noise levels will be minimal; permits are in place.

Environment

This project will not have environmental impacts.

Powerlines 101 - Learning Zone

Learn how the energy grid works; along with our processes to build and maintain electric transmission lines.
Discover about your lines cta btn

Legal

The Virginia State Corporation Commission (SCC) has regulatory authority over all energy providers in Virginia. Among other responsibilities, the SCC validates the need for a proposed line and approves the route and structures. In reviewing a proposed project, the SCC must consider whether potential impacts on scenic assets, historic districts and the environment have been reasonably minimized.

On 9/27/23, Dominion Energy filed its application with the SCC. The SCC issued its Final Order approving the project on 5/31/24. Documents related to the case are available to the public on the SCC Docket of the SCC website or search by Case No. PUR-2023-00168 in the " Search Cases " section. In addition, interested parties may visit the SCC Case Comments Page where individual mailboxes are available for each case accepting public comments.

  • Application Volume 1 of 2 
  • Application Volume 2 of 2 
  • DEQ Report 
  • Meetings

    We have conducted in-person community meetings for learning more about the project and asking questions directly to our subject matter experts. Were you unable to attend? You may also contact us and request a presentation be given to a smaller group in your community.

    June 6, 2023

    6–8 p.m.
    Union Train Station
    103 River Street
    Petersburg, VA 23803

    June 7, 2023

    6–8 p.m.
    Dominion Energy Office
    26306 W Washington St
    Petersburg, VA 23803

    Timeline

    Upcoming

    Summer 2025
    Anticipated construction completion

    2024

    Summer 2024
    Anticipated construction start
    Summer 2024
    SCC Issued Final Order approving project

    2023

    Summer 2023
    Filed application with the Virginia State Corporation Commission (SCC)
    Early Summer 2023
    Community meetings
    Spring 2023
    Project announcement

    FAQs

    Dominion Energy will host a community meeting in Early Summer 2023, at which the public can hear from subject matter experts and ask questions related to the project. You can also contact us to add your mailing address and email address to our distribution list by calling 888-291-0190 or sending an email to powerline@dominionenergy.com.

    Dominion Energy has more than 6,700 miles of overhead transmission lines. The proposed project seeks to replace existing overhead structures with new overhead structures. In doing so, the line will be rebuilt to current safety and industry standards.

    Dominion Energy completes an evaluation of potential environmental, cultural, and historical impacts of the project. We will work with local, state and federal agencies to complete these evaluations and mitigate any impacts. Permitting agencies on transmission line projects typically include the U.S. Army Corps of Engineers, the Virginia Department of Conservation and Recreation, the Virginia Marine Resources Commission, and the Virginia Department of Transportation. Commenting agencies include the Virginia Department of Game and Inland Fisheries and the Virginia Department of Historic Resources, among others. Our enterprise-wide environmental report describes our commitment to the responsible stewardship of natural resources and provides a wealth of information on environmental management and performance. We also invite you to read our Corporate Environmental Policy and our Greenhouse Gas Report.

    Carson-Locks En Español

    Proyecto de reconstrucción de transmisión de energía eléctrica de 230 kV

    En Dominion Energy, nos dedicamos a mantener un servicio de electricidad confiable y seguro en las comunidades que atendemos. El Proyecto de Reconstrucción de la Transmisión de Energía Eléctrica de 230 kilovoltios (kV) Carson-Locks tiene como objetivo reconstruir y cambiar los conductores de 10.34 millas de líneas de transmisión de 230 kV actuales que se expanden desde la Subestación Carson en Ellington Road, ubicada en el Condado de Dinwiddie, hasta la Subestación Locks en Rawlings Lane, ubicada en la Ciudad de Petersburg.

    A fin de mantener un servicio confiable para nuestros clientes, necesitamos reconstruir la línea de transmisión actual desde la Subestación Carson hasta la Subestación Locks. Además de reemplazar los cables de 230 kV actuales, mediante un proceso llamado cambio de conductores, también tendremos que reemplazar las estructuras de transmisión. El cambio de conductores aumentará la ampacidad o la corriente máxima transportada por la línea eléctrica. La línea se reconstruirá dentro del derecho de paso actual; por lo tanto, no se requiere un nuevo derecho de paso permanente. Las líneas se construyeron principalmente con estructuras de marco en H de madera. Proponemos reconstruirlas en gran parte con estructuras de marco en H de acero patinable (marrón), que requieren menos mantenimiento y tienen una mayor vida útil. Las estructuras nuevas serán, en promedio, aproximadamente cinco pies más altas que las estructuras actuales. Este proyecto garantizará la seguridad y la confiabilidad constantes de la red eléctrica.

    Está invitado/a a las reuniones presenciales con la comunidad para informarse más acerca del proyecto y hacer sus preguntas directamente a nuestros expertos en la materia. Elija la fecha y el lugar de la reunión que le resulten más convenientes y pase en cualquier momento entre las 6 y las 8 p. m., tal como se lo permita su agenda. ¿No puede asistir? También puede contactarnos y solicitar que se haga una presentación a un grupo más reducido en su comunidad.

    Beneficios

    • Estructuras nuevas ubicadas en el mismo lugar general que las estructuras actuales
    • Nuevas estructuras situadas en la misma ubicación general que las estructuras existentes
    • Cumple con las normas obligatorias para garantizar la seguridad y la confiabilidad, y satisfacer las necesidades futuras
    • Minimiza el impacto en la comunidad y el medio ambiente

    Cronograma

    • Primavera de 2023: anuncio del proyecto 
    • Principios del verano de 2023: reunión con la comunidad
    • Verano de 2023: presentación de solicitud a la Comisión Estatal de Corporaciones de Virginia (SCC)
    • Verano de 2024: inicio de la construcción anticipada 
    • Verano de 2025: finalización de la construcción anticipada 

    Documentos

    Impactos

    Interrupcion del servicio

    Se estima que su servicio electrico no se vera afectado por este proyecto

    Cercanias

    Este proyecto no producira impactos en el medio ambiente.

    Trafico

    Se estima que este proyecto no afectara el trafico

    Ruido

    Los niveles de ruido seran minimos. Se obtuvieron los permisos necesarios.

    Medio ambiente

    Este proyecto no producira impactos en el medio ambiente.

    Líneas eléctricas - Zona de aprendizaje

    Entérese de cómo funciona la red energética, junto con nuestros procesos para construir y mantener las líneas de transmisión eléctrica.
    Discover about your lines cta btn