Carolina to South Justice Branch Junction

Project Overview

Lineman working at top of bucket truck extended arm on power lines

Rebuild an aging 115 kilovolt (kV) single-circuit electric transmission line to current safety and reliability standards.

It has become necessary to address an aging transmission line which has been in operation since 1959 between our Carolina Substation and the South Justice Branch Junction in Halifax County, North Carolina.

Purpose

It has become necessary to address an aging transmission line which has been in operation since 1959 between our Carolina Substation and the South Justice Branch Junction in Halifax County, North Carolina. This approximately 17.7-mile overhead electric transmission line was originally constructed on wooden H-frame and steel lattice structures. We are rebuilding the entire 115 kV line and parts of the double-circuit 230 kV line in the existing easement using structures similar in appearance and height. All replacement structures will be constructed of brown, weathering steel; new single-circuit structures will be H-frames, and new double-circuit structures will be monopoles. No new right of way is needed.

Benefits

  • Maintains current right of way
  • New structures located in the same general location as existing structures
  • Complies with mandatory standards to ensure safety, reliability and to meet future needs
  • Minimizes impact to the community and environment
  • Replaces aging infrastructure

Timeline

  • LATE 2023: Preconstruction activities, including access installation
  • JANUARY 2024 - DECEMBER 2025: Single-circuit rebuild from Carolina Substation to South Justice Branch Junction
  • APRIL – JUNE 2024: Double-circuit rebuild in Roanoke Rapids
  • SEPTEMBER – NOVEMBER 2024: Double-circuit line work at the I-95 crossing
  • 2026: Continue other transmission line rebuilds in this corridor and begin restoration of right of way

Documents

Project Outcome

Corten Monopole

The double-circuit replacement structures are brown, weathering steel monopoles.

Original Average Height: 115 feet. New Average Height: 120 feet.

White Proposed Tangent


The single-circuit replacement structures are brown, weathering steel H-frames.

Original Average Height: 60 feet. New Average Height: 70 feet.

Most replacements look similar and will be located close to the original structures.

*This rendering is for illustrative purposes only and is not intended for detailed engineering purposes. Actual structure heights and types may vary.

Construction Related Impacts

Service Interruption

Your electric service is not expected to be impacted by this project.

Traffic

This project is not expected to impact traffic.

Noise

Noise levels will be minimal; permits are in place.

Neighborhood

Access to surrounding neighborhoods may be impacted.

Map

Project Map

Timeline

Upcoming

2026
Continue other transmission line rebuilds in this corridor and begin restoration of right of way

2024

September - November 2024
Double-circuit line work at the I-95 crossing
April – June 2024
Double-circuit rebuild in Roanoke Rapids
January 2024 – December 2025
Single-circuit rebuild from Carolina Substation to South Justice Branch Junction

2023

Late 2023
Preconstruction activities, including access installation