Buena Vista-Balcony Falls
Project Overview

The existing structures and components along this 10-mile line corridor have been in service for nearly 10 decades and need to be replaced. We propose replacing the existing galvanized-steel lattice structures primarily with brown, weathering-steel H-frame structures.
Transmission Corridor Conditions
Existing
- Project area is 10 miles long
- Right of way is primarily 100 feet wide with 120-foot and 140-foot sections
- Primarily galvanized steel lattice structures with some galvanized steel monopole structures
Proposed
- Utilize existing right of way corridor
- Install brown, weathering-steel H-frames throughout most of the corridor. Weathering steel monopole and 3-pole structures will be used in some locations.
Benefits
- Maintains current right of way
- New structures located in the same general location as existing structures
- Complies with mandatory standards to ensure safety, reliability and to meet future needs
- Minimizes impact to the community and environment
- Replaces aging infrastructure
Documents
Timeline
Phase 1:
- Late Summer 2024 – Complete construction
- Late Summer 2025 – Begin construction
- Late Summer 2025 –Restoration of work area
- Late Summer 2025 –Begin construction
- Late Summer 2026 –Complete construction
- Late Summer 2026 –Restoration of work area
Construction-Related Impacts

Service Interruption
Your electric service is not expected to be impacted by this project.

Traffic
This project is not expected to impact traffic.

Neighborhood
Access to surrounding neighborhoods will not be impacted.
Map
Timeline
Upcoming
Late Summer 2026
Phase 2: Restoration of work area
Late Summer 2026
Phase 2: Complete construction
Late Fall 2025
Phase 2: Begin construction
Late Summer 2025
Phase 1: Restoration of work area
Late Summer 2025
Phase 1: Complete construction
2024
Late Summer 2024
Phase 1: Begin construction